SWAPNALOK HILL VIEW

Mumbai Suburban · CAARNEEVAL DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700012682

Delivery and registration

When is the project declared for completion?

SWAPNALOK HILL VIEW is registered with MahaRERA as P51700012682 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700012682
Registered on07 Sep 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWAPNALOK HILL VIEW record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWAPNALOK HILL VIEW in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SWAPNALOK HILL VIEW-AWING1-13 Dec 2022
SWAPNALOK HILL VIEW-B WING1G+513 Dec 2022
SWAPNALOK HILL VIEW -ROW HOUSE1-13 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered12 Dec 2023We have completed the project construction and now applying for the occupancy certificate and society formation, therefore requesting the authority to please grant us the certifica
12 Dec 202331 Dec 2025We have completed the project and awaiting the occupancy certificate only a few plots are left unsold. we shall complete the entire project on or before 31.12.2025

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400000. Per the filed land record, the plot is bounded to the north by RESERVIOR, to the south by HILL, to the east by HILL and to the west by DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~79 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park79 km
Andheri MIDC / SEEPZ81 km
Chhatrapati Shivaji Int'l Airport85 km
Bandra Kurla Complex (BKC)86 km
Lower Parel / Worli business district95 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matoshree Nagar

Dwarika Valley Phase III
Past its declared completion date · declared completion Mar 2022 · Dwarika Real Infra LLP

Other RERA-registered projects in Thane

Swapnapurti Homes
possession by Dec 2028 · Niranjan AND A.j. Group Company
Swaraj Heights
declared completion May 2024 · Darshana Samel
Swaraj Orchid
declared completion Mar 2022 · Sandesh Enterprises
Swarajya
possession by Mar 2027 · Sailavkik Realty Private Limited
Swaraswati Heights
possession by Sep 2028 · Shree Samarth Enterprises
Swarg
possession by Jun 2027 · M/s. V.r. Builders

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026