SWASTIK HOUSE

NEAR BANK OF BARODA · SWASTIK CONSTRCUTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007553

Delivery and registration

When is the project declared for completion?

SWASTIK HOUSE is registered with MahaRERA as P51800007553 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007553
Registered on17 Aug 2017
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SWASTIK HOUSE record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 31 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Swastik Constrcution is the promoter of record on 4 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SWASTIK HOUSE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
SWASTIK HOUSE A WING1G+18-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Oct 2021Approved Plans are submitted for Revised and CFo Plans also submitted for Revised
30 Oct 202131 Mar 2025We have already building constructed upto 15th floors as per last Approved Plan & Commencement Certificate. Now we are planning for 16th floor complete and complete compliances for

Location, Land & Connectivity

Located at NEAR BANK OF BARODA, S V ROAD, Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by S V Road, to the south by Plot No 7, to the east by Property of Jam Dhari and to the west by Plot No 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Swastik Legacy
possession by Dec 2028 · Swastik Realtors
Swastik Onyx
declared completion Dec 2025 · Suvasya Builders AND Developers LLP
Swastik Platinum
possession by Dec 2026 · Suvasya Builders AND Developers LLP
Swastik Prabhasa
possession by Dec 2028 · Swastik Realtors
Swastik Revanta
possession by Dec 2028 · Swastik Realtors
Swastik Tulip
possession by Dec 2026 · Swastik Homes

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026