Mumbai/Project record

MahaRERA · the public record

TANISHKA ROYALE

KHOPOLI · NAVKAR CREATIONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

06 Oct 2024declared completionMahaRERA registration · read 12 Jul 2026
30registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

06 Oct 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000027776

Delivery and registration

When is the project declared for completion?

TANISHKA ROYALE is registered with MahaRERA as P52000027776 and the promoter has declared completion for 06 Oct 2024.

06 Oct 2024

declared completion

23months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000027776
Registered on03 Jan 2021
Promoter-declared completion06 Oct 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TANISHKA ROYALE record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Navkar Creations is the promoter of record on 57 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

57projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In TANISHKA ROYALE, ₹3.42 Cr of a declared ₹3.50 Cr estimated project cost is reported as incurred, about 97.8%, as at the last certified filing with MahaRERA.

97.8%

₹3.42 Cr

of ₹3.50 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In TANISHKA ROYALE, 10 of 26 homes filed with MahaRERA are recorded as sold or booked, about 38%, and 16 remain available.

38%sold

10 of 26 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 30 homes in total, while this sold/unsold inventory filing covers 26 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101630 sqft (58.5 sqm)₹41,300
Floor 1103323 sqft (29.98 sqm)-
Floor 1104603 sqft (56 sqm)-
Floor 1105603 sqft (56 sqm)-
Floor 1106323 sqft (29.98 sqm)-
Floor 2204603 sqft (56 sqm)-
Floor 3301630 sqft (58.5 sqm)-
Floor 3305603 sqft (56 sqm)-
Floor 3306323 sqft (29.98 sqm)-
Floor 4401630 sqft (58.5 sqm)-
Floor 4402630 sqft (58.5 sqm)-
Floor 4403323 sqft (29.98 sqm)-
Floor 4406323 sqft (29.98 sqm)-
Ground/Floor 01315 sqft (29.3 sqm)₹55,000
Ground/Floor 03153 sqft (14.2 sqm)₹55,000
Ground/Floor 04131 sqft (12.16 sqm)₹55,000

The inventory filing also declares: 4 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TANISHKA ROYALE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 30 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
TANISHKA ROYALE1G+43007 Oct 2023

Unit mix on the filing: 24 residential and 6 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered06 Oct 2024Respected Sir/Madam, We are requesting you for an extension of the registration for our Project- Tanishka Royale, under the Maharashtra Real Estate Regulatory Authority (MahaRERA)

Location, Land & Connectivity

Located at KHOPOLI, KHOPOLI, Khalapur, Raigarh, 410203. Per the filed land record, the plot is bounded to the north by RAJENDRA LODGE, to the south by ROAD, to the east by ROAD and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~58 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort56 km
Bandra Kurla Complex (BKC)58 km
Lower Parel / Worli business district58 km
Powai / Hiranandani business park58 km
Chhatrapati Shivaji Int'l Airport59 km
Andheri MIDC / SEEPZ62 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khopoli

Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers
Aakash Heights
possession by Dec 2026 · Aakash Lifespaces
Ashiyana Village Building No 10
possession by Dec 2026 · Ajaz Yusuf Khot

Other RERA-registered projects in Raigarh

Tanzanite
possession by Dec 2029 · Kohinoor Developers
TAO Villas
declared completion Mar 2026 · OM Realty
Tapasya-Manasvi Heights
possession by Aug 2027 · VCA SKY Properties
Tapovan Aura
declared completion Dec 2022 · Tapovan Realty
Tara Regency
possession by Apr 2028 · Divya Infra
Taramati Tower Wing I AND J
declared completion Jan 2023 · Vast Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026