TANSA CITY ONE

P51700011576 · promoter Kavya Buildcon Pvt

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP51700011576
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kavya Buildcon Pvt is the promoter of record on 10 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NUMBER 131G+431 Dec 2019
BUILDING NUMBER 141G+431 Dec 2019
BUILDING NUMBER 161G+431 Dec 2019
BUILDING NUMBER 171G+431 Dec 2019
BUILDING NUMBER 181G+431 Dec 2019
BUILDING NUMBER 191G+431 Dec 2019
BUILDING NUMBER 111G+431 Dec 2019
BUILDING NUMBER 121G+431 Dec 2019

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250210026/06/2025SIVA KUMAR vs KAVYA BUILDCON PVT. LTD.order passed
CC1260236922/04/2026Ila Bhupendra Pancholi vs KAVYA BUILDCON PVT. LTD.pending / no order on file

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 421601. Per the filed land record, the plot is bounded to the north by ADJ KHARDI VILLAGE BOUNDARY, to the south by ADJ RAILWAY BOUNDARY LINE, to the east by ADJ GUT NO 156 and to the west by ADJ FOREST BOUNDARY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~71 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park71 km
Andheri MIDC / SEEPZ72 km
Chhatrapati Shivaji Int'l Airport76 km
Bandra Kurla Complex (BKC)77 km
Lower Parel / Worli business district86 km
Nariman Point / Fort92 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kavya Buildcon Pvt. Ltd. is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Kavya Buildcon Pvt. Ltd.

Kavya Buildcon Pvt. Ltd.
Past its declared completion dateThane

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

Tansa City ONE Phase 1 B
declared completion Dec 2022 · Kavya Buildcon Pvt. Ltd.
Tanvi Heights
declared completion Dec 2021 · Tanvi Developers
Tarabai Apartment
declared completion Dec 2019 · Parshuram Developers
Tarabaug
declared completion Dec 2024 · Vidyadhar Achyut Vaishampayan
Tarangan
declared completion May 2018 · Maison Constructions Private Limited
TBC Square
possession by Nov 2029 · Lake Town Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.