Mumbai/Project record

MahaRERA · the public record

The Elements

Ghansoli · TPV Ventures LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

487units filed as unsoldInventory · 20 September 2026
31 Dec 2031declared completionMahaRERA registration · read 12 Jul 2026
581registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700079613

Delivery and registration

When is the project declared for completion?

The Elements is registered with MahaRERA as P51700079613 and the promoter has declared completion for 31 Dec 2031.

31 Dec 2031

declared completion

63months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700079613
Registered on17 Mar 2025
Promoter-declared completion31 Dec 2031
Current statusCertificate Signed
Against today63 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Elements record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In The Elements, ₹55.82 Cr of a declared ₹330.00 Cr estimated project cost is reported as incurred, about 16.9%, as at the last certified filing with MahaRERA.

16.9%

₹55.82 Cr

of ₹330.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In The Elements, 94 of 581 homes filed with MahaRERA are recorded as sold or booked, about 16%, and 487 remain available.

16%sold

94 of 581 homes

₹192.99 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹34.30 Cr (about 18%) is recorded as collected and ₹158.69 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 94 registered agreements, the effective carpet rate is ₹17,516/sqft, with eight in ten falling between ₹14,396 and ₹23,091 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 94 homes carry one, and 487 of the 581 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
51789 sqftRs 1.2400 cr typical, over Rs 1.1268 cr to Rs 1.6931 cr18 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In The Elements, 359 of the 487 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 486 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+50 and 581 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+5082-
Wing B1G+50176-
Wing C1G+5094-
Wing D1G+5094-
Wing E1G+5084-
Commercial1G+551-

Unit mix on the filing: 530 residential and 51 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for The Elements, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
SM1260047815/07/2026Bhakti Achrekar vs TPV Ventures LLPpending / no order on file

Location, Land & Connectivity

Located at Ghansoli , Sector 11, Thane, Thane, 400701. Per the filed land record, the plot is bounded to the north by Plot No 06, to the south by 15 M wide Road, to the east by Plot No 07 and to the west by 34 M Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park9 km
Andheri MIDC / SEEPZ13 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district22 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

TPV Ventures LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by TPV Ventures LLP

Other RERA-registered projects in Ghansoli

Alliaance Icon
possession by Dec 2026 · Satyam Infra
Gami Asters A Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Gami Asters B Wing
possession by Dec 2026 · Thalia AND Gami Enterprises
Kusum Residency
possession by Dec 2026 · Suresh Padman Patil
Goldcrest Residency - Phase 2
possession by Mar 2027 · Savita Homemakers LLP
Century TWO
possession by Mar 2028 · City Infra

Other RERA-registered projects in Thane

THE Enclave
possession by Dec 2027 · Milestone Constructions
The Gateway
possession by Mar 2029 · Metricon Realty LLP
THE Golden Mile
declared completion Dec 2023 · Gracelands Habitats
The Green Sapphirre
possession by Nov 2027 · Green World Realtors
THE Harmony
possession by Dec 2027 · THE Impressions
THE Heavens Palace
possession by Dec 2026 · Gayasuddin Riyazuddin Khan

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026