The Heaven-1

P99000016724 · KONDHAN · promoter Om Gayatri Builder

Certificate SignedDue 31 Mar 2028

Delivery & Registration

MahaRERA registrationP99000016724
Registered on05 Jun 2018
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today20 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Om Gayatri Builder is the promoter of record on 36 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
HEAVEN 1-D1G+131 May 2022
HEAVEN 1-D-11G+131 May 2022
HEAVEN 2-D1G+131 May 2022
HEAVEN 3-D1G+131 May 2022
HEAVEN 3-D-11G+131 May 2022
HEAVEN 4-D1G+131 May 2022
HEAVEN 4-D-11G+131 May 2022
HEAVEN 5-E1G+231 May 2022
HEAVEN 5-E-11G+231 May 2022
HEAVEN 6-E1G+231 May 2022
HEAVEN 7-C-A1G+131 May 2022
HEAVEN 7-C-A-11G+131 May 2022
HEAVEN 7-C-B1G+131 May 2022
HEAVEN 7-C-B11G+131 May 2022
HEAVEN 8-C-A1G+131 May 2022
HEAVEN 8-C-A11G+131 May 2022
HEAVEN 8-C1-B1G+131 May 2022
HEAVEN 8 -C1-B11G+131 May 2022
HEAVEN 8-C1-B21G+131 May 2022
HEAVEN 9-E1G+231 May 2022
HEAVEN 9-E11G+231 May 2022
HEAVEN 10-E1G+231 May 2022
HEAVEN 10-E11G+231 May 2022
HEAVEN 11-D1G+131 May 2022
HEAVEN 11-D11G+131 May 2022
HEAVEN 12-D1G+131 May 2022
HEAVEN 12-D11G+131 May 2022
HEAVEN 13-D1G+131 May 2022
HEAVEN 13-D11G+131 May 2022
HEAVEN 14-D1G+131 May 2022
HEAVEN 14-D11G+131 May 2022
HEAVEN 15-D1G+131 May 2022
HEAVEN 15-D11G+131 May 2022
HEAVEN 16-D1G+131 May 2022
HEAVEN 16-D11G+131 May 2022
HEAVEN 17-F1G+131 May 2022
HEAVEN 18-C-A1G+131 May 2022
HEAVEN 18-C-A11G+131 May 2022
HEAVEN 18-C-A21G+131 May 2022
HEAVEN 18-C1-B1G+131 May 2022
HEAVEN 18-C1-B21G+131 May 2022
HEAVEN 19-C1-B1G+131 May 2022
HEAVEN 19-C-A1G+131 May 2022
HEAVEN 19-C1-B11G+131 May 2022
HEAVEN 19-C-A11G+131 May 2022
HEAVEN 19-C1-B21G+131 May 2022
HEAVEN 19-C-A21G+131 May 2022
HEAVEN COMMERCIO 221G+1231 May 2022
HEAVEN BLDG 21 B1G+1631 May 2022
HEAVEN 21 B11G+1631 May 2022
HEAVEN 20 B1G+1631 May 2022
HEAVEN 20 B11G+1631 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 May 202331 Mar 2028This is unit\villa development project of total 18 Villas. Out of which we have only sold and completed 4 villas. Based on the past experience on project Sale we estimate that we n

Location, Land & Connectivity

Located at KONDHAN, VELGAON ROAD, Mumbai City, Mumbai City, 401404. Per the filed land record, the plot is bounded to the north by VELGAON PADA, to the south by CRD GARDENIA BUILDING PROJECT, to the east by CLOSED SURYA CANAL AND CRD BUNGALOW PROJECT and to the west by ODR ROAD NO 56 VELGAON ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~71 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ71 km
Powai / Hiranandani business park73 km
Chhatrapati Shivaji Int'l Airport76 km
Bandra Kurla Complex (BKC)78 km
Lower Parel / Worli business district86 km
Nariman Point / Fort94 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

OM Gayatri Builder AND Developer is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by OM Gayatri Builder AND Developer

OM Gayatri Builder AND Developer
FlaggedPalghar

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

THE Heaven-2
possession by Dec 2028 · OM Gayatri Builder AND Developer
THE Hill Touch
possession by Dec 2026 · Aristone Infra
THE Midtown
possession by Jun 2027 · Innovision Estates
THE Pancharatna
possession by Dec 2027 · Radhe Builder And Developer
THE Pinnacle
possession by Dec 2026 · Bhakti Enterprise
The Riverrine, Private Riverside Estate
declared completion Dec 2018 · River View Enclave

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026