THE SAGAR CO-OP. HOUSING SOCIETY LTD.

VILEPARLE WEST · J.K.CONSTRUCTION CO.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800021854

Delivery and registration

When is the project declared for completion?

THE SAGAR CO-OP. HOUSING SOCIETY LTD. is registered with MahaRERA as P51800021854 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800021854
Registered on05 Aug 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE SAGAR CO-OP. HOUSING SOCIETY LTD. record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THE SAGAR CO-OP. HOUSING SOCIETY LTD. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
A WING1G+2031 Jul 2022
B WING1G+1531 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILEPARLE WEST, ST FRANCIS ROAD, Borivali, Mumbai Suburban, 400056. Per the filed land record, the plot is bounded to the north by CTS NO 1546, to the south by CTS NO 1563 AND CTS NO 1564, to the east by ST FRANCIS ROAD and to the west by CTS NO 1545 AND CTS NO 1568. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ20 km
Chhatrapati Shivaji Int'l Airport24 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle West

Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP
Meera Kunj
possession by Dec 2026 · Arham Realty

Other RERA-registered projects in Mumbai Suburban

THE Saifee Golden Jubilee Neighbourhood C H S L Unit 1
possession by Dec 2026 · RAJ Builders
The Sanctuary
possession by Jul 2028 · Runwal Construction Private Limited
THE Sanctuary - Tower 2
possession by Mar 2027 · Runwal Construction Private Limited
THE Sanctuary - Tower 4
declared completion Jun 2026 · Runwal Construction Private Limited
THE Sanctuary - Tower 5
declared completion Mar 2026 · Runwal Construction Private Limited
THE Shivram CHS LTD
possession by Dec 2027 · Blackplinth Realtors PVT LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.