THE TRELLIS
KOPARKHAIRANE · MAITHILI BUILDERS PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Mar 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700050980
Delivery and registration
When is the project declared for completion?
THE TRELLIS is registered with MahaRERA as P51700050980 and the promoter has declared completion for 31 Mar 2029.
31 Mar 2029
declared completion
30months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700050980 |
| Registered on | 18 May 2023 |
| Promoter-declared completion | 31 Mar 2029 |
| Current status | Certificate Signed |
| Against today | 30 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE TRELLIS record 13 quarterly progress reports since registration.
13quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Maithili Builders is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
2projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In THE TRELLIS, ₹136.40 Cr of a declared ₹170.00 Cr estimated project cost is reported as incurred, about 80.2%, as at the last certified filing with MahaRERA.
80.2%
₹136.40 Cr
of ₹170.00 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In THE TRELLIS, 125 of 219 homes filed with MahaRERA are recorded as sold or booked (109 with registered agreements and 16 booked), about 57%, and 94 remain available.
57%sold
125 of 219 homes
₹228.81 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹174.82 Cr (about 76%) is recorded as collected and ₹53.99 Cr as receivable. The project registers 432 homes in total, while this sold/unsold inventory filing covers 219 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 125 registered agreements, the effective carpet rate is ₹20,409/sqft, with eight in ten falling between ₹17,994 and ₹24,855 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The inventory filing also declares: 25 not for sale.
What the filings record, home by home
Read from MahaRERA on 19 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 125 homes carry one, and 94 of the 244 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 2007 | 738 sqft | Rs 1.5000 cr typical, over Rs 1.4500 cr to Rs 1.7729 cr | 15 filed on this stack, floors 7–23 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In THE TRELLIS, 87 of the 94 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29 and 432 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| THE TRELLIS WING A | 1 | G+29 | 225 | - |
| THE TRELLIS WING B | 1 | G+27 | 207 | - |
Unit mix on the filing: 417 residential and 15 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | 4595 | 2024 | Pending |
Location, Land & Connectivity
Located at KOPARKHAIRANE, VASHI KOPARKHAIRANE ROAD, Thane, Thane, 400709. Per the filed land record, the plot is bounded to the north by PROPOSED 15 MTR WIDE ROAD, to the south by 6 MTR WIDE ROAD, to the east by PROPOSED 15 MTR WIDE ROAD and to the west by 34 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 11 km |
| Andheri MIDC / SEEPZ | 15 km |
| Chhatrapati Shivaji Int'l Airport | 15 km |
| Bandra Kurla Complex (BKC) | 15 km |
| Lower Parel / Worli business district | 22 km |
| Nariman Point / Fort | 27 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.