Mumbai/Project record

MahaRERA · the public record

TIRUPATI HEIGHTS

KOPAR KHAIRNE · TIRUPATI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700026075

Delivery and registration

When is the project declared for completion?

TIRUPATI HEIGHTS is registered with MahaRERA as P51700026075 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700026075
Registered on15 Aug 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TIRUPATI HEIGHTS record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tirupati Enterprises is the promoter of record on 166 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

166projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TIRUPATI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
TIRUPATI HEIGHTS1G+2031 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOPAR KHAIRNE , PLOT NO 32 SECTOR 9 , Thane, Thane, 400709. Per the filed land record, the plot is bounded to the north by PLOT NO 33, to the south by PLOT NO 31, to the east by PLOT NO 37 and to the west by 24 METER WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tirupati Enterprises is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Tirupati Enterprises

Tirupati Enterprises
Past its declared completion dateRaigarh
Tirupati Enterprises
FlaggedRaigarh

Other RERA-registered projects in Koparkhairane

ONE Luxuria
possession by Dec 2026 · Shakti Pyramid Ventures
Satyam Stella
possession by Dec 2027 · Satyam Superstructures Private Limited
Progressive Era
possession by Dec 2028 · Progressive Homes
Kamdhenu 23 West Grande
possession by Dec 2028 · Accura Developers LLP
Mahalaxmi Heights
possession by Dec 2028 · Mahalaxmi Infra
Satyam Sicilia
possession by Dec 2028 · Sunny Home Makers

Other RERA-registered projects in Thane

Tirupati Namaah
possession by Dec 2030 · Om Shree Tirupati Balaji Builders
Tirupati Pooja
declared completion Dec 2024 · OM Shree Tirupati Balaji Builders
Tirupati Ritu Empire
possession by Dec 2029 · Ritu Corp
Tisai Heights
declared completion Dec 2023 · Tisai Construction
Tisai Residency
possession by Jun 2027 · SKY Touch
Tisai Srushti Phase 1
possession by Dec 2027 · Vvks Developers Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026