MahaRERA Property Intelligence · Raigarh

TOWN CENTRE

P52000011650 · KHOPOLI · promoter Fannan Builders And

Certificate SignedDue 15 Sep 2022

Delivery & Registration

MahaRERA registrationP52000011650
Registered on31 Aug 2017
Promoter-declared completion15 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BUILDING 21G+4-
BUILDING 31G+4-
BUILDING NO 1 PROPOSED1G+5-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000039617012/06/2023Amita Prakash Chaware vs m/s Fannan bUILDERS & DEVELOPERSorder passed
CC00600000036470009/03/2023Viju Namdev Hange vs M/s. Fannan Builders and Developers through its authorized partners & Ors.order passed
CC00600000039594903/06/2023Vijay Khemraj Rathour vs mohammad zahid hussainorder passed
CC1250039305/02/2025Zakir U Dinware vs FANNAN BUILDERS AND DEVELOPERSorder passed
CC1250354805/10/2025manyar vasim dagadu shaikh vs FANNAN BUILDERS AND DEVELOPERSorder passed

Location, Land & Connectivity

Located at KHOPOLI, OLD MUMBAI PUNE HIGHWAY, Khalapur, Raigarh, 410203. Per the filed land record, the plot is bounded to the north by OLD MUMBAI PUNE HIGHWAY, to the south by CTS NO 3059, to the east by CTS NO 3035 and to the west by CST NO 3063. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort50 km
Bandra Kurla Complex (BKC)51 km
Powai / Hiranandani business park51 km
Lower Parel / Worli business district51 km
Chhatrapati Shivaji Int'l Airport53 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khopoli

Daata Eklavya Building A & B
possession by Aug 2026 · Daata Builders And Developers Private Li
Krishna Valley - Phase 3
possession by Aug 2026 · Prishti Venture Private Limited
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers

Major developers building in Khopoli

Other RERA-registered projects in Raigarh

Tranquil Coast
declared completion Jul 2018 · Shankar Baban Gawade
Tricity Aspire
possession by Dec 2029 · Tricity Realty LLP
Tricity Aura
possession by Dec 2028 · Tricity Realty LLP
Tricity Bayview
possession by Dec 2029 · Tricity Realty LLP
Tricity Bliss
possession by Dec 2026 · Tricity Realty LLP
Tricity Crest
possession by Dec 2027 · Tricity Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026