TRILOK GIRIRAJ KRIPA

BORIVALI · KHUSHI SPACES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Jul 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Jul 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800077540

Delivery and registration

When is the project declared for completion?

TRILOK GIRIRAJ KRIPA is registered with MahaRERA as P51800077540 and the promoter has declared completion for 15 Jul 2028.

15 Jul 2028

declared completion

22months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800077540
Registered on20 Aug 2024
Promoter-declared completion15 Jul 2028
Current statusCertificate Signed
Against today22 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TRILOK GIRIRAJ KRIPA record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Khushi Spaces Llp is the promoter of record on 22 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In TRILOK GIRIRAJ KRIPA, ₹6.30 Cr of a declared ₹33.96 Cr estimated project cost is reported as incurred, about 18.6%, as at the last certified filing with MahaRERA.

18.6%

₹6.30 Cr

of ₹33.96 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TRILOK GIRIRAJ KRIPA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
TRILOK GIRIRAJ KRIPA1--

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BORIVALI , CARTER ROAD NO. 4, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by Property of Chimanbhai Patel, to the south by Property of Purshottam Park, to the east by Property of Shanti Kumar Kapadia and to the west by Property of 4th Kasturba Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Khushi Spaces LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Khushi Spaces LLP

Khushi Spaces LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Trilok Heights
possession by Dec 2028 · Rashi Realty
Trilok Park
declared completion Dec 2025 · Rajesh Trilokchand Chopra
Trimbac
declared completion Jun 2026 · DP Buildhomes LLP
Trinity Square
declared completion Jun 2022 · P & K Plinth Pvt. Ltd.
Trinity Towers
possession by Mar 2029 · Jet Speed Realtors Private Limited
Triratna
possession by Jun 2028 · Charkop Triratna CO-Operative Housing So

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026