Mumbai/Project record

MahaRERA · the public record

TULIP PALACE

CHAMBARKHIND · WINGS BUILDCON

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000031885

Delivery and registration

When is the project declared for completion?

TULIP PALACE is registered with MahaRERA as P52000031885 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000031885
Registered on22 Nov 2021
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TULIP PALACE record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Wings Buildcon is the promoter of record on 6 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TULIP PALACE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
TULIP PALACE1G+731 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at CHAMBARKHIND, CHAMBARKHIND, Mahad, Raigarh, 402301. Per the filed land record, the plot is bounded to the north by HISSA NUMBER 03, to the south by INTERNAL WIDE ROAD, to the east by SURVEY NUMBER 114 and to the west by DEVELOPEMENT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1135 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park1135 km
Andheri MIDC / SEEPZ1138 km
Chhatrapati Shivaji Int'l Airport1140 km
Bandra Kurla Complex (BKC)1140 km
Lower Parel / Worli business district1147 km
Nariman Point / Fort1150 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Wings Buildcon is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Wings Buildcon

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
Rukaiya Residence
possession by Dec 2026 · Vision Developers
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana

Other RERA-registered projects in Raigarh

Tulips
declared completion Sep 2023 · M/S Serene Lifespaces
Tulshiram Heights
possession by Dec 2026 · Ajit Raman Gowari
Tulshiram Heights
declared completion Jun 2026 · MS RAM Laxman Developers
Tulshiram Heights
possession by Dec 2030 · Times Property
Tulsi Anmol
declared completion Dec 2024 · Asha Entrade PVT LTD
Tulsi Darshan
declared completion Dec 2019 · Tulsi Estates

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026