UNIMONT CORAL

Dronagiri · RSM HOMES LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000002634

Delivery and registration

When is the project declared for completion?

UNIMONT CORAL is registered with MahaRERA as P52000002634 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000002634
Registered on02 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for UNIMONT CORAL record 37 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for UNIMONT CORAL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
UNIMONT CORAL1G+1431 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023The Promoter have completed the construction work of the project. However it appears that CIDCO is unable to issue Occupancy Certificate at the moment due to issuance of said Coast
30 Dec 202331 Dec 2027As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. I seek extension of the project till 31/12/2027. We have also receive

Location, Land & Connectivity

Located at Dronagiri, Bokadvira, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by 15 MTR WIDE ROAD, to the south by PLOT NO 29, to the east by PLOT NO 35B and to the west by 20 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort15 km
Lower Parel / Worli business district19 km
Bandra Kurla Complex (BKC)23 km
Chhatrapati Shivaji Int'l Airport26 km
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RSM Homes LLP is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by RSM Homes LLP

Other RERA-registered projects in Dronagiri

Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra
Avantika Aura
possession by Dec 2026 · Riddhi Developer
Bombay Chalet
possession by Dec 2026 · Bombay Shiva Plus LLP

Other RERA-registered projects in Raigarh

Unimont Imperia
possession by Aug 2027 · RSM Designers
Unique Residency
declared completion Dec 2018 · Unique Construction
United Emporio
declared completion Jun 2025 · SMB Propertiesllp
United Galaxy Phase 4
declared completion Mar 2019 · The United Group Of Builders And Develop
Unity Homes
declared completion Dec 2025 · Shivam Construction
Unity Ikon
declared completion Sep 2023 · Needa Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026