MahaRERA Property Intelligence · Palghar

UNITED REGENCY

P99000004106 · promoter United Realtors

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP99000004106
Registered on08 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, United Realtors is the promoter of record on 52 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
UNITED REGENCY1G+5-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005711007/12/2018Bhavin Dilip Das vs Bin Amin Gulam Khatri and Sandeep.Malpaniorder passed
CC00600000019645222/03/2021SANGEETA BALI vs United Realtorsorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Dec 2020Project almost Ready for possession but could not apply for OC as it is group housing, and the township infrastrcture is not fully ready,
30 Dec 202130 Dec 2020Construction work of the said building is almost completed but the infrastructure work of the layout is not completed as per the sanction granted by concern authority. Hence we nee

Location, Land & Connectivity

Located at Thane, Thane, 401501. Per the filed land record, the plot is bounded to the north by BUILDING NO 3, to the south by BUILDING NO 1, to the east by BUILDING NO 1 and to the west by BUILDING NO 13. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~76 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ76 km
Powai / Hiranandani business park78 km
Chhatrapati Shivaji Int'l Airport80 km
Bandra Kurla Complex (BKC)82 km
Lower Parel / Worli business district89 km
Nariman Point / Fort97 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

United Realtors is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by United Realtors

Other RERA-registered projects in Boisar

Ostwal Dream Land Phase - II
possession by Jul 2026 · Shree Ostwal Builders LTD
Parvati Homes
possession by Jul 2026 · Iconic Developers
Queens Villa
possession by Jul 2026 · Shashi Kuldeep Ostwal
Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

Major developers building in Boisar

Other RERA-registered projects in Palghar

Unity Garden
declared completion Mar 2018 · Unity Land Developers
Unnatti Anmol
declared completion Dec 2018 · Unnatti Infra
Urban Homes
possession by Jun 2027 · Urban Developers
Utopia
possession by Dec 2027 · Shri Parshva Developers
V-Aqua Villa AND Apartment
declared completion Dec 2022 · V Life Spaces AND Infra Developers Priva
V Square Arcade
possession by Oct 2026 · V Square

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.