MahaRERA Property Intelligence · Raigarh
VAISHNAVI RESIDENCY
P52000027201 · SECTOR 1 · promoter Rk Group Of
Certificate SignedDue 29 Jun 2025
Delivery & Registration
| MahaRERA registration | P52000027201 |
| Registered on | 24 Nov 2020 |
| Promoter-declared completion | 29 Jun 2025 |
| Current status | Certificate Signed |
| Against today | about 13 months past the declared date |
Regulatory Standing
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Builder Track Record
Across MahaRERA, Rk Group Of is the promoter of record on 12 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.
| Building | Wings | Floors | Declared completion |
|---|
| VAISHNAVI RESIDENCY | 1 | G+4 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
Deadline Extensions
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|
| 30 Jun 2023 | 29 Jun 2024 | The project was delayed for reasons beyond our control on account of various unforeseen events. |
| 30 Jun 2023 | 29 Jun 2025 | Due to internal disputes between promoters the project work was on hold, the disputes has now resolved |
Location, Land & Connectivity
Located at SECTOR 1, PUSHPAK NODE, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by 11 MTR ROAD, to the south by PLOT NO 129 AND 130, to the east by PLOT NO 117 and to the west by PLOT NO 119. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
Location & connectivity
The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|
| Powai / Hiranandani business park | 26 km |
| Bandra Kurla Complex (BKC) | 26 km |
| Chhatrapati Shivaji Int'l Airport | 28 km |
| Lower Parel / Worli business district | 29 km |
| Andheri MIDC / SEEPZ | 29 km |
| Nariman Point / Fort | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
Unlock in the ₹999 report →
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
Unlock in the ₹2,999 report →
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Unlock in the ₹999 report →
Should you buy in VAISHNAVI RESIDENCY?
This page is the free MahaRERA filing summary.
The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
✓ Independent — we don't broker these flats✓ Built only from official MahaRERA filings✓ Money-back if it doesn't help your decision
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Builder track record
RK Group OF Infra is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
- Vaishnavi Pride — Past its declared completion date
- Vaishnavi Hill View — Past its declared completion date
Other flagged projects by RK Group OF Infra
RK Group OF Infra
FlaggedRaigarh
RK Group OF Infra
FlaggedRaigarh
RK Group OF Infra
Past its declared completion dateRaigarh
RK Group OF Infra
Past its declared completion dateRaigarh
Other RERA-registered projects in Panvel
Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises
Major developers building in Panvel
The Wadhwa Group · 30 projects hereUnder construction: Magnolia Cluster 1 · Magnolia Cluster 2 · Magnolia Cluster 3 · Magnolia Cluster 4 · Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1 · Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A2 · Wise City, South Block Phase I, Plot RZ8 Building 2 Wing B3 · Wise City, South Block Phase I, Plot Rz8 Building 3 Wing C1 · Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F3 · Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4 Pride Purple · 3 projects hereUnder construction: Apramit
Completion date passed: Pride Cottage · Pride Villa Puravankara · 2 projects hereUnder construction: Badridham
Completion date passed: Sai Dham Godrej · 1 project hereCompletion date passed: Godrej City Panvel Ph.1 Kanakia · 1 project hereCompletion date passed: Kanakia Greenberg
Other RERA-registered projects in Raigarh
Vaishnavi Residency
declared completion Dec 2025 · Anil Tukaram Waghmare
Vaishnavi Residency
declared completion Dec 2025 · Vibrant Landchester
Vaishnovi Heights
declared completion Mar 2020 · Vaishnovi Construction Company
Vakratund
declared completion Jun 2023 · Santosh Dattu Patil
Vakratunda Residency
declared completion Jul 2018 · S Cube Buildcon
Vakratunda Residency
declared completion Jun 2023 · Greenfield Developers
What to verify before you book
- Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
- Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
- Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
- Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.
Last checked against the RERA register: 27 Jul 2026