MahaRERA Property Intelligence · Thane

VARDHAMAN VATIKA PHASE iii BUILD NO 3

P51700021541 · VASIND WEST · promoter Vardhaman Venture

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP51700021541
Registered on08 Jul 2019
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vardhaman Venture is the promoter of record on 45 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
VARDHAMAN VATIKA BUILDING NO 31G+431 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2023POJECT IS READY OCCUPATION CERTIFCATE PENDING

Location, Land & Connectivity

Located at VASIND WEST, MUMBAI NASHIKHIGHWAY, Shahapur, Thane, 421601. Per the filed land record, the plot is bounded to the north by VARDHAMAN VATIKA PHASE i, to the south by SARMAL ROAD, to the east by MUMBAI NASHIK HIGHWAY and to the west by PLOT 302. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~154 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park154 km
Andheri MIDC / SEEPZ155 km
Chhatrapati Shivaji Int'l Airport159 km
Bandra Kurla Complex (BKC)161 km
Lower Parel / Worli business district169 km
Nariman Point / Fort176 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vardhaman Venture is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Vardhaman Venture

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

Vardhman Garden Phase 1
declared completion Dec 2019 · Diwali Construction Company
Vardhman Garden Phase II
declared completion Dec 2023 · Diwali Construction Company
Vardhman Vatika
declared completion Dec 2019 · Diwali Developers
Varhaala Heights
possession by Mar 2028 · Sarvashiva Enterprises
Varija Apartment
declared completion Mar 2021 · Ganesha Developers
Varsha Heights
possession by Dec 2027 · B K Groups

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026