MahaRERA Property Intelligence · Mumbai Suburban

Veena Insignia

PM1180002400053 · Adarsh Nagar · promoter Veena Infratech Llp

Certificate SignedDue 31 Mar 2030

Delivery & Registration

MahaRERA registrationPM1180002400053
Registered on07 Oct 2024
Promoter-declared completion31 Mar 2030
Current statusCertificate Signed
Against today44 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Veena Infratech Llp is the promoter of record on 176 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~17.7% of the estimated project cost incurred as of the last certificate (₹41.15 Cr spent against a ₹232.54 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 133 homes filed with MahaRERA, 30 are sold/booked and 103 remain available (~23% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹111.86 Cr in agreement value so far. Of that, ₹32.96 Cr (~29%) is already collected, ₹78.89 Cr receivable — a read on how far along these sales really are. Note: the project registers 217 homes in total, but this sold/unsold inventory filing covers only 133 of them — the other 84 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 30 registered agreements, the effective carpet rate is ₹33,374/sqft (typical range ₹32,912–₹41,844) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35 and 217 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building 11G+35217-

Unit mix on the filing: 210 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202831 Mar 2030Site mobilization delay not involving any government bottleneck

Location, Land & Connectivity

Located at Adarsh Nagar, New Link Road, Borivali, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by 13 40 M Wide existing road, to the south by Sangam Cooperative Housing Society, to the east by 36 60 M Wide existing road and to the west by Shiv Shivam Tower. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)10 km
Lower Parel / Worli business district17 km
Nariman Point / Fort25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Veena Infratech LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Veena Infratech LLP

Veena Infratech LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Veena Santoor Phase II
declared completion Dec 2019 · Veena Developers
Veena Senterio
declared completion Dec 2024 · Veena Realcon Private Limited
Veena Serene-Residential
declared completion Jun 2025 · Veena Realcon Private Limited
Veena Serenity
declared completion Dec 2021 · Veena Realcon Private Limited
Veena Signature
declared completion Dec 2019 · Veena Developers
Veena Smart Homes
declared completion Jun 2025 · V.d. Infratech Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026