VINAY GARDENS

SAPHALE WEST · VINAY REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000020588

Delivery and registration

When is the project declared for completion?

VINAY GARDENS is registered with MahaRERA as P99000020588 and the promoter has declared completion for 30 Apr 2024.

30 Apr 2024

declared completion

29months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000020588
Registered on26 Apr 2019
Promoter-declared completion30 Apr 2024
Current statusCertificate Signed
Against todayabout 29 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VINAY GARDENS record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VINAY GARDENS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
VINAY GARDENS BUILDING NO 11G+930 Jul 2021
VINAY GARDENS BUILDING NO 21G+430 Jul 2021
VINAY GARDENS BUILDING NO 51G+430 Jul 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 May 2023The Project is being constructed in the Rural Areas which frequently faces shortage of Material and Manpower and Shortage of Electricity. The Project had faced acute shortages of M
31 May 202330 Apr 2024Respected Sir, We hereby state and request for the Extension of the said Project. The said entire Project is Entirely Completed from our end and it is also certified by architect a

Location, Land & Connectivity

Located at SAPHALE WEST, STATION ROAD, JUNCTION OF SAPHALE PALGHAR LINK ROAD, Thane, Thane, 401102. Per the filed land record, the plot is bounded to the north by 12 MTS WIDE EXISTING ROAD, to the south by SURVEY NO 231 PART, to the east by 9 MTS WIDE EXISTING ROAD and to the west by 24 MTS WIDE EXISTING ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vinay Realty is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vinay Realty

Vinay Realty
Past its declared completion datePalghar

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

Vinay Gardens Building NO 3 AND 4
declared completion Apr 2024 · Vinay Realty
Vinay Unique Imperia
declared completion Dec 2019 · Imperium Buildcon LLP
Vinay Unique Residency Bldg NO 10 Known AS SKY
possession by Sep 2028 · Jasamrit Estates Private Limited
Vinay Unique Residency Bldg NO 10 Known AS-SKY
possession by Dec 2029 · Jasamrit Estates Private Limited
Vinay Unique Residency Bldg NO 7 A Wing
possession by Dec 2026 · Jasamrit Estates Private Limited
Vinayak Enclave
possession by Mar 2027 · SJA Infraheights Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.