VRINDAVAN FLORA-RASAYANI GARDEN-PHASE I

Rees · THALIA LABHA HOME PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000012120

Delivery and registration

When is the project declared for completion?

VRINDAVAN FLORA-RASAYANI GARDEN-PHASE I is registered with MahaRERA as P52000012120 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000012120
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VRINDAVAN FLORA-RASAYANI GARDEN-PHASE I record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Thalia Labha Home is the promoter of record on 16 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VRINDAVAN FLORA-RASAYANI GARDEN-PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
RASAYANI GARDEN-BUILDING NO 31G+431 Dec 2020
RASAYANI GARDEN- BUILDING NO 11G+631 Dec 2019
RASAYANI GARDEN- BUILDING NO 21G+930 Dec 2021
RASAYANI GARDEN- BUILDING NO 41G+731 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Rees, Panvel, Raigarh, 410222. Per the filed land record, the plot is bounded to the north by GAT NO 101, to the south by GAT NO29, to the east by GAT NO 17-1 and to the west by GAT NO 101. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort50 km
Bandra Kurla Complex (BKC)51 km
Powai / Hiranandani business park51 km
Lower Parel / Worli business district51 km
Chhatrapati Shivaji Int'l Airport53 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Thalia Labha Home Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Rees

Balaji Tulips
possession by Nov 2026 · Balaji Homes
Latitude-Status Redefined
possession by Dec 2026 · Flexton Lifespaces Private Limited
Jyoti Residency
possession by Mar 2027 · Janvi Enterprises
Shree Aangan - A Wing
possession by Dec 2027 · Shiv Creators LLP
Triratna Complex
possession by Dec 2027 · Empire Builders AND Developers
Aashray Nisarg
possession by Jun 2028 · Aashray Homes

Other RERA-registered projects in Raigarh

Vrindavan Heights
possession by Dec 2033 · Sahajanand Infratech
Vrindavan Home Phase 2
possession by Dec 2026 · Shree Rujve Enterprises
Vrindavan Homes Phase 3
possession by Dec 2031 · Vandu Builder LLP
Vrindavan Phase - I
declared completion Dec 2019 · Sunny Builders AND Developers
Vrindavan Phase - II
possession by Dec 2027 · Sunny Builders AND Developers
Vrindavan Riverside
possession by Dec 2026 · Greenscape Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026