Mumbai/Project record

MahaRERA · the public record

WADHAN INDUSTRIAL ESTATE

Mumbai City · GANESH KRUPA ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900008692

Delivery and registration

When is the project declared for completion?

WADHAN INDUSTRIAL ESTATE is registered with MahaRERA as P51900008692 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900008692
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for WADHAN INDUSTRIAL ESTATE record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for WADHAN INDUSTRIAL ESTATE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
WADHAN INDUSTRIAL ESTATE A1G+2-
WADHAN INDUSTRIAL ESTATE B1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ward FSouth, Mumbai City, 400012. Per the filed land record, the plot is bounded to the north by 12 MTR ROAD, to the south by SURVEY NO 50, to the east by SURVEY NO 45 and to the west by NALA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)123 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parel

Inspire
possession by Sep 2026 · R K Constructions
K RAS Residency
possession by Sep 2026 · K RAS Group
Kinjal Pride
possession by Oct 2026 · Hi Rock Construction Pvt Ltd
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Ruparel Jewel
possession by Dec 2026 · Renuka Realtors

Major developers building in Parel

Other RERA-registered projects in Mumbai City

Wadhwa Pristine
declared completion Dec 2024 · Wadhwa Group Holdings Private Limited
Waterfront Tower
declared completion Jul 2023 · Sea Kunal Corporation Pvt. Ltd.
Waterview
possession by Jun 2028 · Lodha Developers Limited
Western India Mill
declared completion Dec 2017 · Mhada
Westside
possession by Mar 2028 · Bhuvnesh Enterprises
White Flower Residency
possession by Dec 2026 · White Flowers Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026