Noida/Project record

UP-RERA · the public record

Aims Golf Avenue

Gautam Buddha Nagar · AIMS PROMOTERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2017declared completionUP-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

UP-RERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

UP-RERA · UPRERAPRJ6895

Registration and delivery

What does the register record for this project?

Aims Golf Avenue is registered with UP-RERA, and the promoter has declared completion for 31 Dec 2017.

31 Dec 2017

declared completion

Figures are the promoter's own filings as they stood when Quietlist last read the register. A declared completion date is a filing, not a handover commitment.

Source · UP-RERA project register · read 20 Sep 2026

Legal and disputes

What complaints are recorded?

69 project-level complaints are recorded against AIMS GOLF AVENUE (PHASE -1) on UP-RERA.

69on this project

3promoter projects

registered with UP-RERA

Counts as published on the UP-RERA register. The complaint documents are not on the public record, so the page reports the counts only.

Source · UP-RERA project and promoter register

Official Filing Snapshot

Official fieldUP-RERA value
Project typeOngoing
Registration date14-08-2017
Proposed period22 months
Promoter projects on UP-RERA3
Promoter complaints on UP-RERA90 (Under Registration - 0 )
Project complaints on UP-RERA69

Buyer Paperwork Checklist

Buyer documentStatusUP-RERA row
Agreement for salenot listed-
Allotment letternot listed-
Conveyance deednot listed-
Encumbrance declarationnot listed-
Form-B affidavitnot listed-
Commencement certificatenot listed-
Occupancy/completion proformaon fileProforma of Completion Certificate(Occupancy)

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Sector 18 commercial5 km
Noida Expressway (Sec 125–142)5 km
Sector 62 IT hub6 km
Connaught Place, Delhi17 km
IGI Airport, Delhi27 km
Noida Int'l Airport, Jewar55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Aims Promoters.

If the declared completion date has passed

  1. Ask the developer for the latest RERA extension filing and the revised possession date.
  2. Check your allotment letter's possession clause for interest or compensation on delay.
  3. Verify whether the project has an updated completion date on the UP-RERA portal.
  4. File a complaint with UP-RERA if the delay is beyond the registered deadline and no extension has been filed.

Your rights as a buyer (RERA)

  • Section 18 — Interest on delay: You are entitled to interest at SBI MCLR+1% on every instalment paid, for each month of delay, until possession or refund.
  • Section 19 — Right to refund: If the builder cannot deliver possession, you may claim a full refund of all amounts paid, with interest.
  • Section 31 — File a complaint: Buyers can file directly with UP-RERA. The builder is required to respond within the prescribed period.

What this record tells you — and what to verify

This page is the free UP-RERA filing summary: registration, the developer-declared completion date, and completion-certificate status. It does not show quarter-by-quarter construction progress or project-level buyer complaints — UP-RERA keeps those off the free record — so before you commit money, verify:

Other RERA-registered projects in Sector 75

Major developers building in Sector 75

"Declared completion" is the date filed with UP-RERA by the developer; passing it flags the declared timeline, not a claim about actual handover. Explore every project on our Noida project-timeline tool.

Own a unit in Aims Golf Avenue?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026