The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
29 Mar 2022
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
UP-RERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
UP-RERA · UPRERAPRJ5465
Registration and delivery
What does the register record for this project?
Sushant Aquapolis, Group Housing, Phase-2 is registered with UP-RERA, and the promoter has declared completion for 29 Mar 2022.
29 Mar 2022
declared completion
1extension
recorded on the register
Figures are the promoter's own filings as they stood when Quietlist last read the register. A declared completion date is a filing, not a handover commitment.
Source · UP-RERA project register · read 20 Sep 2026
Legal and disputes
What complaints are recorded?
28 project-level complaints are recorded against SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A (Default on QPR) on UP-RERA.
28on this project
3promoter projects
registered with UP-RERA
Counts as published on the UP-RERA register. The complaint documents are not on the public record, so the page reports the counts only.
Source · UP-RERA project and promoter register
Official Filing Snapshot
| Official field | UP-RERA value |
|---|---|
| Project type | Ongoing |
| Registration date | 10-08-2017 |
| Proposed period | 102 months |
| Promoter projects on UP-RERA | 3 |
| Promoter complaints on UP-RERA | 236 (Under Registration - 0 ) |
| Project complaints on UP-RERA | 28 |
Buyer Paperwork Checklist
| Buyer document | Status | UP-RERA row |
|---|---|---|
| Agreement for sale | not listed | - |
| Allotment letter | listed, verify file | Proforma of Allotment Letter |
| Conveyance deed | listed, verify file | Proforma of Conveyance Deed |
| Encumbrance declaration | listed, verify file | Details of Encumbrances |
| Form-B affidavit | listed, verify file | Affidavit (Form-B) |
| Commencement certificate | listed, verify file | Commencement Certificate |
| Occupancy/completion proforma | listed, verify file | Proforma of Completion Certificate(Occupancy) |
Builder Record
Ansal has 31 other Noida-region projects in the records checked; 27 are past their declared completion date with no clean OC/CC signal — but because UP-RERA publishes OCs inconsistently, a project that has actually been delivered can still read this way. Read it as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate.
- Builtups Zone I - declared 2019-04-08
- Sushant Serene Residency Ph1 T7b1 & T6d - declared 2019-09-30
- Fairway Zone-3 - declared 2019-12-31
- Ansal Sumangalam Corporate Suites - declared 2019-12-31
Location & Connectivity
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Sector 62 IT hub | 7 km |
| Noida Expressway (Sec 125–142) | 12 km |
| Sector 18 commercial | 13 km |
| Connaught Place, Delhi | 22 km |
| IGI Airport, Delhi | 35 km |
| Noida Int'l Airport, Jewar | 59 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.