Pune/Project record

MahaRERA · the public record

157 158 Guruwar Peth

Guruwar Peth · PRATHMESH CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

02 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

02 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100027936

Delivery and registration

When is the project declared for completion?

157 158 Guruwar Peth is registered with MahaRERA as P52100027936 and the promoter has declared completion for 02 Jun 2023.

02 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100027936
Registered on21 Jan 2021
Promoter-declared completion02 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 157 158 Guruwar Peth record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Prathmesh Construction is the promoter of record on 14 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

14projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 157 158 Guruwar Peth in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
157 158 Guruwar Peth1G+603 Dec 2021

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for 157 158 Guruwar Peth, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000019802711/01/2023FIROZ IBRAHIM SHIKALGAR vs M/S PARTHMESH CONSTRUCTIONorder passed
CC00500000019806813/01/2023IMAMBI MAHAMMAD HANIF INAMDAR vs M/S PARTHMESH CONSTRUCTIONorder passed
CC00500000019806711/01/2023FARUK ISAK SAYYED vs M/s PARTHMESH CONSTRUCTIONorder passed
CC00500000019808915/01/2023ANIL BABUSA KHANAPURE vs M/S PARTHMESH CONSTRUCTIONorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered02 Jun 2023Project Delayed due to covid restrictions

Location, Land & Connectivity

Located at Guruwar Peth, 157 158, Pune City, Pune, 411042. Per the filed land record, the plot is bounded to the north by 1 M Lane, to the south by 6 M Lane, to the east by 4 M Lane and to the west by 4 M Lane. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Guruwar Peth

Sanghvi Premio
possession by Oct 2026 · Nitin Kantilal Sanghvi
Samaira Tower
possession by Nov 2026 · Prathamesh Constro Realty Llp
Shri Balaji Sudarshan
Deregistered by MahaRERA · possession by Dec 2026 · Shri Balaji Sudarshan
Radiance
Not filing quarterly progress reports · possession by Dec 2026 · Mohammed Sabir Husain Shaikh
Siddhi Plaza
possession by Dec 2026 · Shree Developers
TEJ Nova
possession by Dec 2027 · Tejraj Profile Infra LLP

Other RERA-registered projects in Pune

15th Street Avenue
possession by Jun 2027 · Raviraj Realties And Capital Limited
16 Lakaki
possession by Dec 2026 · Shah Kulkarni Associates LLP
17 East
possession by Sep 2026 · Platinum Properties
17 Insignia
possession by Mar 2029 · Insignia Associates
17 Monica Classic
possession by Dec 2028 · Not Available
172W Inclusive Housing
declared completion Jun 2026 · Vilas Javdekar Lifestyle Developers Pvt.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026