Pune/Project record

MahaRERA · the public record

51 SIBERIA

DHANORI TALUKA · BUNTY PROPERTIES UNIT NO VII

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024342

Delivery and registration

When is the project declared for completion?

51 SIBERIA is registered with MahaRERA as P52100024342 and the promoter has declared completion for 30 Mar 2025.

30 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024342
Registered on05 Feb 2020
Promoter-declared completion30 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 51 SIBERIA record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bunty Properties Unit is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 51 SIBERIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
51 SIBERIA A WING1G+631 Mar 2024
51 SIBERIA B WING1G+631 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DHANORI TALUKA , S. NO 27/1A/1 , Pune City, Pune, 411015. Per the filed land record, the plot is bounded to the north by adj by road, to the south by adj by sr no27 2, to the east by Adj by part of survey no 27 1a 1 and to the west by asj by sr no67 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)3 km
Kharadi / EON IT Park7 km
Pune Junction / city centre7 km
Magarpatta / Hadapsar IT9 km
Baner–Balewadi belt13 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers
Aaiji Crystal Phase II
possession by Oct 2026 · Aaiji Developers
Galaxy Co-Operative Housing Society Ltd
possession by Oct 2026 · Yash Developers
Austin
possession by Dec 2026 · Krishna Venture Skyscraper LLP

Major developers building in Dhanori

Other RERA-registered projects in Pune

51B Inclusive Housing
declared completion Dec 2025 · Vilas Javdekar Eco Housing Private Limit
534, Kasba
declared completion Dec 2025 · Sagar Bandal Associate
54 Flores Drive Phase 1
possession by Jun 2029 · Swaraj Landmarks LLP
54 Flores Drive Phase 2
possession by Jun 2031 · Swaraj Landmarks LLP
55 Shashwat Avenue
possession by Dec 2027 · Shashwat Landmark
56 Kings Avenue
possession by Dec 2028 · Vastushree Infra Reality

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026