Pune/Project record

MahaRERA · the public record

86 SAHNEY SUJAN PARK

MUNJERI · STALION BUILDCON LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100025305

Delivery and registration

When is the project declared for completion?

86 SAHNEY SUJAN PARK is registered with MahaRERA as P52100025305 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100025305
Registered on05 Apr 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 86 SAHNEY SUJAN PARK record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 86 SAHNEY SUJAN PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
86 SAHNEY SUJAN PARK1G+630 Jun 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MUNJERI, MUNJERI, Haveli, Pune, 411040. Per the filed land record, the plot is bounded to the north by BY PUBLIC ROAD, to the south by BY PLOT NO 81, to the east by BY ROAD and to the west by BY PLOT NO 85. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wanawadi

Gold Crest
possession by Dec 2026 · Golden Magnum
Mainland Eternia
possession by Dec 2026 · Mainland Spaces LLP
Revanta
possession by Dec 2026 · Surana Landmarks LLP
The Deva Residences
possession by Dec 2026 · Suresh Devendra Kothari HUF
Ram Residency
possession by Jan 2027 · Opulent Builders
Ishanand
possession by Jun 2027 · Makawana Bros & CO

Other RERA-registered projects in Pune

9 Dhanlaxmi
possession by Feb 2028 · Ajit Construction & Builders LLP
9 Jagdish
possession by Mar 2027 · Trisha Constrotech
9 Luxure Estates
declared completion Nov 2019 · SVB Realty Pvt Ltd
9-Nanded
possession by Sep 2027 · Purandar Promoters AND Builders
9 Sadashiv C Building
possession by Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
9 Tara Crest
possession by Mar 2030 · Srichaitanya Space Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026