Aditya Complex Phase 2

Near Mahadev Mandir Gavthan · Rohidas Maruti Jadhav

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100016827

Delivery and registration

When is the project declared for completion?

Aditya Complex Phase 2 is registered with MahaRERA as P52100016827 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100016827
Registered on18 Jun 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aditya Complex Phase 2 record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rohidas Maruti Jadhav is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aditya Complex Phase 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
C Wing1G+431 Dec 2020
D Wing1G+431 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2022DUE TO COVID 19 WE WERE UNABLE TO COMPLETE PROJECT ON TIME
30 Dec 202231 Dec 2024Due to Completion Certificate not received from Corporation.

Location, Land & Connectivity

Located at Near Mahadev Mandir Gavthan, Panchshil Nagar, Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by By Road and there after property of Survey No 67, to the south by By property of survey no 66 4 A, to the east by By Property of Survey No 66 5 and to the west by By property of Survey No 66 3. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Aditya Enclave
possession by Mar 2027 · Rakhi Pankaj Chopada
Aditya Green City
possession by Dec 2027 · Aditya Promoters
Aditya Icon
declared completion May 2018 · Aditya Buildcon
Aditya Pride
declared completion Jul 2023 · Aditya Paradise
Aditya Pride C1
declared completion Jan 2024 · Aditya Paradise
Aditya Shubham
possession by Mar 2030 · Not Available

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.