Pune/Project record

MahaRERA · the public record

AMAR PRAKRITI

Donaje · Eternity Buildcon LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

05 Feb 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

05 Feb 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100030089

Delivery and registration

When is the project declared for completion?

AMAR PRAKRITI is registered with MahaRERA as P52100030089 and the promoter has declared completion for 05 Feb 2025.

05 Feb 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100030089
Registered on29 Jul 2021
Promoter-declared completion05 Feb 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMAR PRAKRITI record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Eternity Buildcon Llp is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In AMAR PRAKRITI, 124 of 244 plots filed with MahaRERA are recorded as sold or booked, about 51%, and 120 remain available.

51%sold

124 of 244 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMAR PRAKRITI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered05 Feb 2025Please refer to explanatory note enclosed to extension application given in Annexure E

Location, Land & Connectivity

Located at Donaje, Sinhgad Road, Pune City, Pune, 411025. Per the filed land record, the plot is bounded to the north by Gat No 111 114 115 and proposed phase 2 Gat No 117, to the south by Gat No 120 part and Donaje village boundary, to the east by Gat No 119 Proposed Phase II and to the west by Gat No 121. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Gorhe Bk

OM Tapovan
possession by Dec 2026 · OM Tapovan
Panna Niwas
possession by Dec 2026 · Unique Developers
Vrundavan
possession by Jun 2027 · SAI Ganesh Associates
Mindspace Villas Phase I
possession by Dec 2028 · MS Lifestyle Resorts
Pakhar 2 AND 3 BHK Nests
possession by Dec 2028 · Royal Developers AND Builders
The Back Water Residency Phase II - B Building
Deregistered by MahaRERA · declared completion Dec 2025 · LNK Projects Through Proprietor Mr Naray

Other RERA-registered projects in Pune

Amar Serenity
declared completion Dec 2021 · Amar Builders AND Developers
Amar Serenity Wing E Lig/mig Building
declared completion Oct 2019 · Parth Developers
Amar Summit
possession by Dec 2027 · Silverleaf Associates LLP
Amar Westview
declared completion Dec 2018 · INC Developers
Amara
declared completion Sep 2024 · Raghunath & Sons Promoters & Bui
Amara
possession by Dec 2030 · Bansall Amara LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026