Pune/Project record

MahaRERA · the public record

ANAND PLAZA

WARJE · DHANASHREE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

12units filed as unsoldInventory · 20 September 2026
31 Dec 2029declared completionMahaRERA registration · read 12 Jul 2026
19registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1260002502804

Delivery and registration

When is the project declared for completion?

ANAND PLAZA is registered with MahaRERA as PM1260002502804 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

39months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPM1260002502804
Registered on16 Mar 2026
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today39 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANAND PLAZA record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dhanashree Developers is the promoter of record on 8 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In ANAND PLAZA, 0 of 12 units filed with MahaRERA are recorded as sold or booked, about 0%, and 12 remain available.

0%sold

0 of 12 units

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 19 units in total, while this sold/unsold inventory filing covers 12 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1B-103228 sqft (21.15 sqm)₹18.10 Lakh
Floor 1B-104235 sqft (21.82 sqm)₹18.67 Lakh
Floor 1B-105422 sqft (39.17 sqm)₹33.51 Lakh
Floor 2B-201710 sqft (65.98 sqm)₹56.45 Lakh
Floor 2B-202712 sqft (66.13 sqm)₹56.58 Lakh
Floor 2B-203228 sqft (21.15 sqm)₹18.10 Lakh
Floor 2B-204235 sqft (21.82 sqm)₹18.67 Lakh
Floor 2B-205422 sqft (39.17 sqm)₹33.51 Lakh
Floor 3B-301609 sqft (56.59 sqm)₹42.10 Lakh
Floor 3B-302609 sqft (56.59 sqm)₹42.10 Lakh
Floor 3B-305162 sqft (15.09 sqm)₹11.23 Lakh
Floor 3B-307291 sqft (27 sqm)₹20.09 Lakh

The inventory filing also declares: 7 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANAND PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, unit by unit

Read from MahaRERA on 20 September 2026

No unit in ANAND PLAZA carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 12 units — the Annual Statement of Rates valuation, with each unit’s carpet area and floor already applied. Across them that is Rs 7,949 a sq ft typical, over Rs 6,911 to Rs 7,949.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the unit to you.

The Reckoner Record lists all 12 of them — each unit, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 12 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 19 units are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ANAND PLAZA1G+319-

Unit mix on the filing: 7 residential and 12 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at WARJE, -, Haveli, Pune, 411058. Per the filed land record, the plot is bounded to the north by ODHA, to the south by 12.00 M WIDE SERVICE RAOD, to the east by S. NO 129 PART and to the west by S. NO 129 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre9 km
Baner–Balewadi belt9 km
Magarpatta / Hadapsar IT13 km
Hinjewadi Rajiv Gandhi IT Park14 km
Kharadi / EON IT Park16 km
Pune Int'l Airport (Lohegaon)17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dhanashree Developers is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Warje

Libero
Not filing quarterly progress reports · possession by Dec 2026 · Satish Bora AND Associates
Ketan Heights Wing / Building No A
possession by Dec 2026 · Ketandevelopers
LE Phoenix
possession by Dec 2026 · Taksh Buildcon
Gulab Shilp
possession by Mar 2027 · Buttepatil Properties
Warje Business Bay
possession by Mar 2027 · Sanvi Developers
Cavansite Phase 2
possession by Jun 2027 · Arma Landmark LLP

Other RERA-registered projects in Pune

Anand Residency
declared completion Jan 2023 · S R Builders
Anand Residency
declared completion Dec 2018 · Medankar Shevkari Associates
Anand Sagar
possession by May 2036 · Sunshine Associates
Anand Sagar Residency
possession by Mar 2028 · Shripad Builders & Developers
Anand Terrace
possession by Sep 2029 · Not Available
Anand Terraces A Building
possession by Dec 2028 · Ashish Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026