ANANDGRAM PAUD PHASE II

Paud · VASTUSHODH REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005012

Delivery and registration

When is the project declared for completion?

ANANDGRAM PAUD PHASE II is registered with MahaRERA as P52100005012 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005012
Registered on09 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANANDGRAM PAUD PHASE II record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vastushodh Realty is the promoter of record on 13 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANANDGRAM PAUD PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
A1G+931 Jul 2022
B1G+931 Jul 2022
C1G+931 Jul 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ANANDGRAM PAUD PHASE II, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002339710/09/2019Dilip Vaman Karnataki vs Vastushodh SS Realtyorder passed

Location, Land & Connectivity

Located at Paud, Pune Mulshi, Haveli, Pune, 412108. Per the filed land record, the plot is bounded to the north by 12 MTR WIDE INTERNAL ROAD OF ANANDGRAM PAUD PROJEC, to the south by PROPOSED CLUB HOUSE OF ANANDGRAM PAUD PROJECT, to the east by AMENITY SPACE OF ANANDGRAM PAUD PROJECT and to the west by 12 MTR WIDE INTERNAL ROAD OF ANANDGRAM PAUD PROJEC. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park15 km
Baner–Balewadi belt18 km
Pune Junction / city centre28 km
Pune Int'l Airport (Lohegaon)33 km
Magarpatta / Hadapsar IT33 km
Kharadi / EON IT Park35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vastushodh Realty is the promoter on 4 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vastushodh Realty

Vastushodh Realty
Past its declared completion datePune
Vastushodh Realty
Past its declared completion datePune

Other RERA-registered projects in Paud

Playtor Paud D- Phase 2
Deregistered by MahaRERA · possession by Sep 2026 · Sangam Realty
Shivangan
possession by Nov 2026 · R M Developers Pune
Nishigandh, B Wing
possession by Dec 2026 · Nirmiti Realities
Satvam Hills C4
possession by Dec 2026 · Symphony Landmarks LLP
Sparsh Aster
possession by Dec 2026 · Shree Enterprises
Terra Casa - Grande
possession by Dec 2026 · Ambika Realty

Other RERA-registered projects in Pune

Anandgram Paud Phase III
declared completion Jul 2023 · Vastushodh Realty
Anandi
possession by Dec 2029 · SAI Developers
Anandi Madhav Smruti
possession by Dec 2026 · Sehgnor Developers LLP
Anandi Malhar
possession by Dec 2027 · Reliable Constructions
Anandi Residency
declared completion Dec 2019 · RS Constructions
Anandi Vihar
possession by Dec 2028 · Sanskruti Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026