MahaRERA Property Intelligence · Pune

ANKUR INFRA

P52100050936 · Plot No 8,9,10, GatNo 170/A/2, Katphal, Tal Baramati, Dist Pune, Pin 413133 · promoter Ankur Infra

Certificate SignedDue 31 Mar 2028

Delivery & Registration

MahaRERA registrationP52100050936
Registered on15 May 2023
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today20 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ankur Infra is the promoter of record on 22 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~26.9% of the estimated project cost incurred as of the last certificate (₹70.00 Lakh spent against a ₹2.60 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 30 homes filed with MahaRERA, 0 are sold/booked and 30 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1Flat No.101432 sqft (40.11 sqm)₹9.95 Lakh
Floor 1Flat No.102432 sqft (40.11 sqm)₹9.95 Lakh
Floor 1Flat No.103567 sqft (52.64 sqm)₹13.06 Lakh
Floor 1Flat No.104432 sqft (40.11 sqm)₹9.95 Lakh
Floor 1Flat No.105432 sqft (40.11 sqm)₹9.95 Lakh
Floor 2Flat No.201432 sqft (40.11 sqm)₹9.95 Lakh
Floor 2Flat No.202432 sqft (40.11 sqm)₹9.95 Lakh
Floor 2Flat No.203567 sqft (52.64 sqm)₹13.06 Lakh
Floor 2Flat No.204432 sqft (40.11 sqm)₹9.95 Lakh
Floor 2Flat No.205432 sqft (40.11 sqm)₹9.95 Lakh
Floor 3Flat No.301432 sqft (40.11 sqm)₹9.95 Lakh
Floor 3Flat No.302432 sqft (40.11 sqm)₹9.95 Lakh
Floor 3Flat No.303567 sqft (52.64 sqm)₹13.06 Lakh
Floor 3Flat No.304432 sqft (40.11 sqm)₹9.95 Lakh
Floor 3Flat No.305432 sqft (40.11 sqm)₹9.95 Lakh
Floor 4Flat No.401432 sqft (40.11 sqm)₹9.95 Lakh
Floor 4Flat No.402432 sqft (40.11 sqm)₹9.95 Lakh
Floor 4Flat No.403567 sqft (52.64 sqm)₹13.06 Lakh
Floor 4Flat No.404432 sqft (40.11 sqm)₹9.95 Lakh
Floor 4Flat No.405432 sqft (40.11 sqm)₹9.95 Lakh
Floor 5Flat No.501432 sqft (40.11 sqm)₹9.95 Lakh
Floor 5Flat No.502432 sqft (40.11 sqm)₹9.95 Lakh
Floor 5Flat No.503567 sqft (52.64 sqm)₹13.06 Lakh
Floor 5Flat No.504432 sqft (40.11 sqm)₹9.95 Lakh
Floor 5Flat No.505432 sqft (40.11 sqm)₹9.95 Lakh
Floor 6Flat No.601432 sqft (40.11 sqm)₹9.95 Lakh
Floor 6Flat No.602432 sqft (40.11 sqm)₹9.95 Lakh
Floor 6Flat No.603567 sqft (52.64 sqm)₹13.06 Lakh
Floor 6Flat No.604432 sqft (40.11 sqm)₹9.95 Lakh
Floor 6Flat No.605432 sqft (40.11 sqm)₹9.95 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 30 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ANKUR INFRA1G+630-

Unit mix on the filing: 30 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202631 Mar 2028Due to unforeseen circumstances, the project could not be completed within the original timeline. Delays in material procurement, labour shortages, logistical issues, and regulator

Location, Land & Connectivity

Located at Plot No 8,9,10, GatNo 170/A/2, Katphal, Tal Baramati, Dist Pune, Pin 413133, Katphal, Baramati, Pune, 413133. Per the filed land record, the plot is bounded to the north by Plot No 7, to the south by Gat No 196, to the east by 9 Mtr Wide Road and to the west by Gat No 170 A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rui

Mayureshwar Mall
possession by Oct 2026 · Mayureshwar Associates
Muktai Prime
possession by Dec 2026 · New Muktai Builders
Subhadra Phase 3
possession by Dec 2026 · Subhadra Constructions
Rajnakshatra Palace
possession by Mar 2027 · Devgiri Buildcon
Mayureshwar Pride
possession by Apr 2027 · Mayureshwar Construction
Sujit Pride
possession by Feb 2029 · Tanishq Builders And Developers

Other RERA-registered projects in Pune

Ankur Projects
declared completion Dec 2022 · Ankur Projects
Ankur Residency
possession by Oct 2026 · Ankur Developers
Anmol
possession by Jun 2027 · Builtwell Constructions
Anmol Residency
declared completion Jun 2023 · Anmol Developers
Anna Awas
declared completion Oct 2024 · Muktai Developers
Annapurna
declared completion Nov 2023 · Devki Housing PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026