Pune/Project record

MahaRERA · the public record

APOORVA APARTMENT CONDOMINIUM

Erandwane · M/S. FORTUNE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

05 Oct 2028declared completionMahaRERA registration · read 12 Jul 2026
6registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

05 Oct 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1260002501230

Delivery and registration

When is the project declared for completion?

APOORVA APARTMENT CONDOMINIUM is registered with MahaRERA as PR1260002501230 and the promoter has declared completion for 05 Oct 2028.

05 Oct 2028

declared completion

25months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1260002501230
Registered on15 Oct 2025
Promoter-declared completion05 Oct 2028
Current statusCertificate Signed
Against today25 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for APOORVA APARTMENT CONDOMINIUM record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Fortune Developers is the promoter of record on 122 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

122projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In APOORVA APARTMENT CONDOMINIUM, ₹4.20 Cr of a declared ₹30.50 Cr estimated project cost is reported as incurred, about 13.8%, as at the last certified filing with MahaRERA.

13.8%

₹4.20 Cr

of ₹30.50 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for APOORVA APARTMENT CONDOMINIUM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2 and 6 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
APOORVA APARTMENT CONDOMINIU1G+26-

Unit mix on the filing: 6 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Erandwane , Prabhat Road Lane no.1 1 , Pune City, Pune, 411004. Per the filed land record, the plot is bounded to the north by ADJ.F.PLOT NO.38/15, to the south by EXISTING 15.00M WIDE ROAD, to the east by PROPOSED 6.00M W.ROAD and to the west by ADJ.F.PLOT NO.38/16. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre5 km
Baner–Balewadi belt8 km
Magarpatta / Hadapsar IT10 km
Pune Int'l Airport (Lohegaon)12 km
Kharadi / EON IT Park12 km
Hinjewadi Rajiv Gandhi IT Park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. Fortune Developers is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every M/s. Fortune Developers project & its RERA track record →

Other flagged projects by M/s. Fortune Developers

M/s. Fortune Developers
FlaggedPune
M/s. Fortune Developers
FlaggedPune
M/s. Fortune Developers
FlaggedPune
M/s. Fortune Developers
FlaggedPune
M/s. Fortune Developers
FlaggedPune

Other RERA-registered projects in Erandwane

Madhumati Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Serenity Springs
possession by Sep 2026 · Buttepatil Properties
State Bank OF India Employees Himgauri CO Operative Housing Society LTD
possession by Sep 2026 · Fortune Developers
Swojas Maitree
possession by Sep 2026 · Swojas Enterprises
THE Pleasant CO OP Housing Society LTD
possession by Sep 2026 · Shree Venkatesh Landmarks
Venkatesh Erandwane Central - Building-B1 - Phase 2
possession by Sep 2026 · Shree Venkatesh Buildcon PVT LTD

Major developers building in Erandwane

Other RERA-registered projects in Pune

Apostrophe Hinjawadi Tower A
possession by Dec 2028 · Hinjawadi Infradevelopment PVT LTD
Apostrophe Hinjawadi Tower B
possession by Dec 2027 · Hinjawadi Infradevelopment PVT LTD
Apostrophe Next
declared completion Dec 2022 · Kasturi Builders
Apple Aroma
declared completion Jun 2019 · Apple Buildcon
Apple Blossom
declared completion Mar 2022 · Yashodhan Properties
Apple Galaxy
declared completion Mar 2022 · Apple Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026