Pune/Project record

MahaRERA · the public record

AQUA VIE

Aadgaon · Pavan Hooja, Veena Hooja, Varun Hooja, Sanat Hooja

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2031declared completionMahaRERA registration · read 10 Sep 2026
Certificate Signedregistration statusMahaRERA registration · read 10 Sep 2026

The record · free to read

Registration read 10 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 10 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1260002601298

Delivery and registration

When is the project declared for completion?

AQUA VIE is registered with MahaRERA as PM1260002601298 and the promoter has declared completion for 30 Apr 2031.

30 Apr 2031

declared completion

55months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 10 Sep 2026

MahaRERA registrationPM1260002601298
Registered on24 Jul 2026
Promoter-declared completion30 Apr 2031
Current statusCertificate Signed
Against today55 months to the declared date

Promoter record

What else is this promoter on record for?

Pavan Hooja Veena is the promoter of record on 26 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

26projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 10 Sep 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AQUA VIE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 10 Sep 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2031NA

Location, Land & Connectivity

Located at Aadgaon, -, Andheri, Mumbai Suburban, 412108. Per the filed land record, the plot is bounded to the north by Tata Lake, to the south by Lonavala to Paud Road / Gat No. 152, 151, to the east by Tata Land and to the west by Tata Land. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park35 km
Baner–Balewadi belt39 km
Pune Junction / city centre49 km
Pune Int'l Airport (Lohegaon)54 km
Magarpatta / Hadapsar IT55 km
Kharadi / EON IT Park56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Paud

Playtor Paud D- Phase 2
Deregistered by MahaRERA · possession by Sep 2026 · Sangam Realty
Shivangan
possession by Nov 2026 · R M Developers Pune
Nishigandh, B Wing
possession by Dec 2026 · Nirmiti Realities
Satvam Hills C4
possession by Dec 2026 · Symphony Landmarks LLP
Sparsh Aster
possession by Dec 2026 · Shree Enterprises
Terra Casa - Grande
possession by Dec 2026 · Ambika Realty

Other RERA-registered projects in Pune

Aquagem
declared completion Jun 2025 · Namrata Realty
Aquila
possession by Sep 2028 · Dilip Baburao Tupe
Aqura Indraprastha
possession by Apr 2030 · Aqura Builder And Developer Private Limi
Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Aqura Pride Wing A
possession by May 2028 · Aqura Builder And Developer Private Limi
Aqura Prime
possession by Apr 2027 · Aqura Builder And Developer Private Limi

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 2 Sep 2026