Aura Sai Krishnangan-Building B

Koregaon Bhima · Bhagvati Infra

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19units filed as unsoldInventory · 12 September 2026
31 Aug 2022declared completionMahaRERA registration · read 12 Jul 2026
49registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005017

Delivery and registration

When is the project declared for completion?

Aura Sai Krishnangan-Building B is registered with MahaRERA as P52100005017 and the promoter has declared completion for 31 Aug 2022.

31 Aug 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005017
Registered on09 Aug 2017
Promoter-declared completion31 Aug 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aura Sai Krishnangan-Building B record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bhagvati Infra is the promoter of record on 22 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Aura Sai Krishnangan-Building B, 12 of 31 homes filed with MahaRERA are recorded as sold or booked, about 39%, and 19 remain available.

39%sold

12 of 31 homes

₹1.93 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1.16 Cr (about 60%) is recorded as collected and ₹77.28 Lakh as receivable. The project registers 49 homes in total, while this sold/unsold inventory filing covers 31 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 12 registered agreements, the effective carpet rate is ₹9,287/sqft, with eight in ten falling between ₹5,658 and ₹11,793 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1Office-106150 sqft (13.97 sqm)₹7.45 Lakh
Floor 1Office-110145 sqft (13.5 sqm)₹7.20 Lakh
Floor 2Office-201197 sqft (18.34 sqm)₹9.40 Lakh
Floor 2Office-203131 sqft (12.15 sqm)₹6.58 Lakh
Floor 2Office-205150 sqft (13.97 sqm)₹7.45 Lakh
Floor 2Office-209495 sqft (45.99 sqm)₹22.00 Lakh
Floor 2Office-210145 sqft (13.5 sqm)₹7.20 Lakh
Floor 3Office-303131 sqft (12.15 sqm)₹6.58 Lakh
Floor 3Office-304127 sqft (11.81 sqm)₹6.45 Lakh
Floor 3Office-310145 sqft (13.5 sqm)₹7.20 Lakh
Floor 4Office-401197 sqft (18.34 sqm)₹9.40 Lakh
Floor 4Office-402131 sqft (12.19 sqm)₹6.60 Lakh
Floor 4Office-403131 sqft (12.15 sqm)₹6.58 Lakh
Floor 4Office-404127 sqft (11.81 sqm)₹6.45 Lakh
Floor 4Office-405150 sqft (13.97 sqm)₹7.45 Lakh
Floor 4Office-409495 sqft (45.99 sqm)₹22.00 Lakh
Floor 4Office-410145 sqft (13.5 sqm)₹7.20 Lakh
Ground/Floor 0Shop-5186 sqft (17.24 sqm)₹8.90 Lakh
Ground/Floor 0Shop-9648 sqft (60.21 sqm)₹28.50 Lakh

The inventory filing also declares: 18 not for sale.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 12 homes carry one, and 19 of the 49 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
Office-402131 sqftRs 11.00 lakh typical, over Rs 8.30 lakh to Rs 12.17 lakh3 filed on this stack, floors 1–3

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today.

In Aura Sai Krishnangan-Building B, 3 of the 19 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 18 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 49 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
B-Commercial building1G+54931 Jul 2019

Unit mix on the filing: 49 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Aug 2022TECHNICAL DIFFICULTIES

Location, Land & Connectivity

Located at Koregaon Bhima, Koregaon Bhima, Haveli, Pune, 412216. Per the filed land record, the plot is bounded to the north by AMENITY PLOT AREA AS PER SANCTIONED PLAN, to the south by OPEN SPACE AS PER SANCTIONED PLAN, to the east by adj gat no 422 and to the west by 12 mtr wide internal road as per sanctioned plan. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)17 km
Kharadi / EON IT Park17 km
Magarpatta / Hadapsar IT21 km
Pune Junction / city centre24 km
Baner–Balewadi belt32 km
Hinjewadi Rajiv Gandhi IT Park35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Bhagvati Infra is the promoter on 5 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Bhagvati Infra project & its RERA track record →

Other flagged projects by Bhagvati Infra

Bhagvati Infra
Past its declared completion datePune
Bhagvati Infra
Past its declared completion datePune
Bhagvati Infra
Past its declared completion datePune

Other RERA-registered projects in Lonikand

AUM Aangan
Deregistered by MahaRERA · possession by Dec 2026 · Kamdhenu Spaces LLP
Green City
possession by Dec 2026 · Not Available
OXY Flora Phase 3
possession by Dec 2026 · Yogesh Developers
Tulsi Villa
possession by Dec 2026 · Vinod Chandrakant Magar ( Prop. Yashoda
Tulsi Villa
possession by Dec 2026 · MR Rajendra Narayan Kand (yashoda Proper
Suburbia Estate Phase 1
possession by Feb 2027 · SSG Realty AND Infra LLP

Other RERA-registered projects in Pune

Aura Vrisa
possession by Dec 2028 · Not Available
Aura Waters Phase -I
possession by Dec 2026 · Ranawat Properties
Aura Waters Phase II
possession by Dec 2029 · Ranawat Properties
Aurapolis
possession by Dec 2029 · Krishna Choice Spaces LLP
Aureate
possession by Dec 2027 · M/s Shree Omkareshwar Developers
Aurelia
possession by Dec 2026 · Shitole Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026