30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013637

Delivery and registration

When is the project declared for completion?

Belshore 11,12,13,14,15,16,17,18 LCL - 0010 is registered with MahaRERA as P52100013637 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013637
Registered on16 Oct 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Belshore 11,12,13,14,15,16,17,18 LCL - 0010 record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Lavasa Corporation Ltd is the promoter of record on 31 projects registered with MahaRERA, 31 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

31flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Belshore 11,12,13,14,15,16,17,18 LCL - 0010 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Belshore 111G+5-
Belshore 121G+5-
Belshore 131G+5-
Belshore 141G+5-
Belshore 151G+5-
Belshore 161G+5-
Belshore 171G+5-
Belshore 181G+5-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Belshore 11,12,13,14,15,16,17,18 LCL - 0010, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001044924/10/2017Krishna Kumar Maurya vs Lavasaorder passed
CC00500000001198202/09/2018Suresh Joshi vs M/s Lavasa Corporation Ltd.order passed

Legal & Litigation

The promoter has declared 16 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Additional Collector36/20172017Hearing
Additional CollectorRTS/2/APPEAL/1138/2016, RTS/2/APPEAL/1139/2016, RTS/2/APPEAL/1140/2016, TS/2/APPEAL/1141/2016, RTS/2/APPEAL/1142/2016, RTS/2/APPEAL/1143/2016, RTS/2/APPEAL/1144/20162016Order Is Passed By Additional Collector Agaisnt Lcl
Additional CollectorRTS/2/APPEAL/36/2017, RTS/2/APPEAL/37/2017, RTS/2/APPEAL/38/2017, RTS/2/APPEAL/39/2017, RTS/2/APPEAL/40/2017, RTS/2/APPEAL/41/2017, RTS/2/APPEAL/42/20172017Hearing
Sub Divisional OfficerRTS No 72/2017, RTS No 73/2017, RTS No 74/2017, RTS No 77/2017, RTS No 78/2017, RTS No 79/2017, RTS No 80/20172017Hearing
High Court Bombay2 of 20092009Hearing
High Court Bombay129 of 20142010Hearing
High Court Bombay109 of 20132013Hearing
Ngt Pune9 of 20122012Hearing
Ngt Pune36 of 20112011Hearing
High Court BombayCP No 902/20152015For Admission
High Court BombayCP No 368 / 20162016For Admission
High Court BombayCP No330/2016 CP No501/2016 CPL /725/20162016For Admission
Nclt MumbaiTCP/408/20172017For Admission
Drt MumbaiOA No18 of 20172017Hearing
Nclt MumbaiCP/1462/20172017For Admission
High Court BombayCP 1586/20172017For Admission

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 412112. Per the filed land record, the plot is bounded to the north by Ravine, to the south by Mugaon Lake, to the east by East Lake Front Street and to the west by Mugaon Lake. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Hinjewadi Rajiv Gandhi IT Park10 km
Pune Junction / city centre12 km
Magarpatta / Hadapsar IT17 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lavasa Corporation Ltd is the promoter on 31 MahaRERA-registered projects, of which 31 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lavasa Corporation Ltd project & its RERA track record →

Other flagged projects by Lavasa Corporation Ltd

Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune
Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune
Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune
Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune
Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune
Lavasa Corporation Ltd
Developer in insolvency (NCLT)Pune

Other RERA-registered projects in Pune

Belshore 1,2,3,4,5,6,7,8,9,10 LCL - 0009
Developer in insolvency (NCLT) · declared completion Dec 2025 · Lavasa Corporation Ltd
Hillshore 1,2,3,4,5,6,7,8,9,10,11 LCL - 0012
Developer in insolvency (NCLT) · declared completion Dec 2025 · Lavasa Corporation Ltd
Brookview 1,2,3,4,5 LCL 0001
Developer in insolvency (NCLT) · declared completion Dec 2021 · Lavasa Corporation Ltd
Centrino Lcl0002
Developer in insolvency (NCLT) · declared completion Dec 2021 · Lavasa Corporation Ltd
Club View 1,2,3,9,10,11 LCL 0003
Developer in insolvency (NCLT) · declared completion Dec 2021 · Lavasa Corporation Ltd
Club View 12, 13 - Lcl0005
Developer in insolvency (NCLT) · declared completion Dec 2021 · Lavasa Corporation Ltd

Other RERA-registered projects in Pune

Belvedere
possession by Apr 2027 · Agarwal Infratech
Belview
possession by Jul 2030 · Tranquil Infratech LLP
Bestate Axis
possession by Apr 2028 · Bestate Commercial Development Company
Beverly Hills Plot A
declared completion Nov 2024 · Sachin Laldas Tapkir
Beverly Hills Plot B
declared completion Nov 2024 · Komal Sachin Tapkir
Beverly Hills Plot C
declared completion Nov 2024 · Ravi Laxman Landge

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026