MahaRERA Property Intelligence · Pune

BOUGAIN VILLA - CLUSTER 1

P52100011902 · promoter Gangotree Homes Holidays

Certificate SignedDue 31 Dec 2031

Delivery & Registration

MahaRERA registrationP52100011902
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2031
Current statusCertificate Signed
Against today65 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Gangotree Homes Holidays is the promoter of record on 34 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 40 homes filed with MahaRERA, 29 are sold/booked and 11 remain available (~72% sold) — selling steadily. Buyers have committed ₹4.49 Cr in agreement value so far. Of that, ₹4.49 Cr (~100%) is already collected, ₹0 receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 29 registered agreements, the effective carpet rate is ₹1,718/sqft (typical range ₹900–₹6,174) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1A1-1653 sqft (60.67 sqm)₹15.00 Lakh
Floor 1B5648 sqft (60.21 sqm)₹15.00 Lakh
Floor 1D1383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D10383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D11361 sqft (33.55 sqm)₹15.00 Lakh
Floor 1D12383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D13383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D2383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D7383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D8383 sqft (35.55 sqm)₹15.00 Lakh
Floor 1D9383 sqft (35.55 sqm)₹15.00 Lakh

⚠ The inventory filing also declares: 1 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0 and 41 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A11G+01-
A21G+01-
A31G+01-
A41G+01-
C11G+01-
C21G+01-
A51G+01-
A61G+01-
B11G+01-
B21G+01-
B31G+01-
B41G+01-
A71G+01-
A1-11G+01-
A1-21G+01-
A1-31G+01-
A1-41G+01-
A1-51G+01-
A1-61G+01-
A1-71G+01-
A1-81G+01-
A1-91G+01-
A1-101G+01-
A1-111G+01-
A1-121G+01-
B51G+01-
B61G+01-
D11G+0101 Dec 2020
D21G+0101 Dec 2020
D31G+01-
D41G+01-
D51G+01-
D61G+01-
D71G+01-
D81G+01-
D91G+01-
D101G+01-
D111G+01-
D121G+02-
Restaurant1G+01-
Bougain Villa - Cluster 11G+0--

Unit mix on the filing: 40 residential and 1 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
01 Dec 202131 Dec 2031The following are the explanatory reasons setting out grounds and reasons for the delay in the completion of our said project: 1. I, Mr. Rajendra Dnyaneshwar Awate, Partner of M/s.

Location, Land & Connectivity

Located at Bhor, Pune City, Pune, 412206. Per the filed land record, the plot is bounded to the north by Gat 656, to the south by Gat 620 621 622, to the east by Gat 629 627 640 and to the west by Gat 632 633. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~42 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT42 km
Pune Junction / city centre43 km
Kharadi / EON IT Park46 km
Baner–Balewadi belt46 km
Pune Int'l Airport (Lohegaon)49 km
Hinjewadi Rajiv Gandhi IT Park51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gangotree Homes & Holidays is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Gangotree Homes & Holidays

Gangotree Homes & Holidays
Past its declared completion datePune
Gangotree Homes & Holidays
FlaggedPune
Gangotree Homes & Holidays
FlaggedPune

Other RERA-registered projects in Bhor

Parvati Apartment
possession by Sep 2026 · Sagar Shivram Shete
Prospera County
possession by Oct 2026 · Mudraa Life Spaces PVT LTD
Aarya Green County
possession by Dec 2027 · Nirmitee Developers
Marigolds Valley
possession by Dec 2027 · Castle Dream Space
Swapnalok Nagari, Bhor, Building NO. 4
Deregistered by MahaRERA · possession by Dec 2027 · Swapnalok Developers
Villament
possession by Dec 2027 · Gangotree Homes AND Holidays

Major developers building in Bhor

Other RERA-registered projects in Pune

Bougain Villa - Cluster 2
declared completion Dec 2021 · Gangotree Homes & Holidays
Bougain Villa - Cluster 3
possession by Dec 2031 · Gangotree Homes & Holidays
Boulevard Part Of Towers Phase 1
declared completion Apr 2024 · Bramhacorp Limited
Boulevard Tower A1
declared completion Dec 2025 · Bramhacorp Limited
Boulevard Tower A2
possession by Dec 2026 · Bramhacorp Limited
Boulevard Wing B 1
possession by Dec 2028 · Bramhacorp Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026