Pune/Project record

MahaRERA · the public record

Chandrai Orchid

Bhosari · Manisha Ravindra Landge

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007263

Delivery and registration

When is the project declared for completion?

Chandrai Orchid is registered with MahaRERA as P52100007263 and the promoter has declared completion for 31 Jul 2022.

31 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007263
Registered on17 Aug 2017
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Chandrai Orchid record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Manisha Ravindra Landge is the promoter of record on 99 projects registered with MahaRERA, 21 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

99projects

registered with MahaRERA

21flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Chandrai Orchid in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Chandrai Orchid1G+731 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2022There is no booking in the said project so as to meet the construction cost because of which the construction of the project is not completed & delay in project

Location, Land & Connectivity

Located at Bhosari, Kasarwadi, Haveli, Pune, 411034. Per the filed land record, the plot is bounded to the north by CTS no 2623 2623 Hissa no 2, to the south by CTS no 2600 2601, to the east by CTS no 2613 and to the west by CTS no 2614 Hissa no 1 2614 Hisssa no 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt7 km
Hinjewadi Rajiv Gandhi IT Park8 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)13 km
Kharadi / EON IT Park16 km
Magarpatta / Hadapsar IT17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kasarwadi

Unity Park
possession by Dec 2026 · Shriram Vision
Vishal Complex E Wing
possession by Mar 2027 · Vishal Chordiya Constructions Private Li
Square 9
possession by Jun 2027 · Skyline Builders & Developers
Chaitanya Apartments
possession by Dec 2027 · Vishwatmak Realtors LLP
Parshwa Green Edge
possession by Aug 2028 · Shreyas Ashokkumar Pagariya
Mathura Vaibhav
possession by Dec 2028 · Lande Patil Associates

Major developers building in Kasarwadi

Other RERA-registered projects in Pune

Chandrama Aangan
declared completion Dec 2022 · Chandrama Construction
Chandrama- B Wing
declared completion Mar 2026 · Trimurti Associates
Chandrangan
possession by Dec 2029 · Shreenath Auto Works & Service Stati
Chandrangan Rajgad
possession by Dec 2026 · Chandrangan Buildcon
Chandrangan Revanta
possession by Dec 2028 · Chandrangan Buildcon LLP
Chandrangan Revanta C Wing
possession by Dec 2026 · Chandrangan Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026