MahaRERA Property Intelligence · Pune

CHAVAN ECO VILLAGE

P52100007278 · promoter Pratap Laxman Chavan

Certificate SignedDue 01 Jan 2021

Delivery & Registration

MahaRERA registrationP52100007278
Registered on17 Aug 2017
Promoter-declared completion01 Jan 2021
Current statusCertificate Signed
Against todayabout 66 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pratap Laxman Chavan is the promoter of record on 40 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
AO1-01 Jan 2022
A11G+501 Jan 2022
A21G+501 Jan 2022
A31G+501 Jan 2022
B11G+501 Jan 2022
B21-01 Jan 2022
C11-01 Jan 2022
C21G+501 Jan 2022
D11G+501 Jan 2022
D21-01 Jan 2022
ROWHOUSE UNIT NO 11G+101 Jan 2022
ROWHOUSE UNIT NO 21G+101 Jan 2022
ROWHOUSE UNIT NO 31G+101 Jan 2022
ROWHOUSE UNIT NO 41G+101 Jan 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by 207, to the south by 205, to the east by 206 and to the west by 203. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~79 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT79 km
Kharadi / EON IT Park80 km
Pune Int'l Airport (Lohegaon)84 km
Pune Junction / city centre85 km
Baner–Balewadi belt96 km
Hinjewadi Rajiv Gandhi IT Park101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pratap Laxman Chavan is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Pratap Laxman Chavan

Other RERA-registered projects in Baramati

Nirvana Elite
possession by Jul 2026 · Akash Jayesh Associates
Sharada Baug
possession by Aug 2026 · Mandar Shrikant Sikachi
G G Capital
possession by Aug 2026 · GG Builders AND Developers
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers
Gadhavenanaware Heights
possession by Sep 2026 · Shri Developers
Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon

Major developers building in Baramati

Other RERA-registered projects in Pune

Chavan ECO Village A0, B2, C1 AND D2
possession by Mar 2028 · Pratap Laxman Chavan
Chavan Garden
possession by Apr 2032 · M/S Chavan Construction
Chavan Paradise - Phase I
declared completion Jun 2026 · B K Chavan Builders PVT LTD
Chavan Paradise - Phase II
declared completion Dec 2022 · B K Chavan Builders PVT LTD
Cherish
declared completion Jul 2023 · Rajendra Abaji Bhosale
Cherry Hills Building A
declared completion Mar 2026 · Not Available

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026