DAFFODILLS

Pune · VIJAY HARI MULAY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004308

Delivery and registration

When is the project declared for completion?

DAFFODILLS is registered with MahaRERA as P52100004308 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004308
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DAFFODILLS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In DAFFODILLS, 40 of 55 plots filed with MahaRERA are recorded as sold or booked, about 73%, and 15 remain available.

73%sold

40 of 55 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DAFFODILLS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 10 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your plot. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Junior Division Bhor2162012Transferred To Civil Judge Senior Division Pune
Civil Judge Senior Division Pune9132016Suit Is Transferred From Civil Judge Junior Division Bhor Is Pending
Civil Judge Senior Division Pune16582013Pending
District Judge Pune952016Pending
Court Of Sub Divisional Officer Bhor2692011Decided And Order Passed
Court Of Sub Divisional Officer Bhor5722012Decided And Order Passed
Court Of Additional Collector Pune11492016Pending
Court Of Additional Collector Pune11502016Pending
Judicial Magistrate Bhor162014Pending
Judicial Magistrate Bhor1442015Pending

Location, Land & Connectivity

Located at Haveli, Pune, 412206. Per the filed land record, the plot is bounded to the north by BY SURVEY NO 57 , to the south by BY BOUNDRY OG VILLAGE GAVADI, to the east by BY SURVEY NO 54 50 51 47 45 42 AND 39 and to the west by BY BOUNDRY OF VILLAGE MHALWADI . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt111 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhor

Parvati Apartment
possession by Sep 2026 · Sagar Shivram Shete
Prospera County
possession by Oct 2026 · Mudraa Life Spaces PVT LTD
Aarya Green County
possession by Dec 2027 · Nirmitee Developers
Marigolds Valley
possession by Dec 2027 · Castle Dream Space
Swapnalok Nagari, Bhor, Building NO. 4
Deregistered by MahaRERA · possession by Dec 2027 · Swapnalok Developers
Villament
possession by Dec 2027 · Gangotree Homes AND Holidays

Major developers building in Bhor

Other RERA-registered projects in Pune

Daffodils
declared completion Mar 2025 · Ojas Associates
Daffodils Avenue Phase 2
declared completion Mar 2018 · Pentagon Shreemangal Vishhram Ventures
Dahlia
possession by Jun 2028 · K Square Builders LLP
Daine Heights
declared completion Dec 2021 · Gosafe Builders AND Developers
Daksha Enclave
possession by Dec 2027 · Ajit Govindlal Mutha
Damodar Bhoomi
declared completion Dec 2021 · Rohit Rajiv Sheth

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026