MahaRERA Property Intelligence · Pune

Dixit Sneh Sankul Phase 1

P52100032280 · Nene Ghat · promoter Sahasrabudhe Kanitkar Associates

Certificate SignedDue 31 Aug 2024

Delivery & Registration

MahaRERA registrationP52100032280
Registered on22 Dec 2021
Promoter-declared completion31 Aug 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sahasrabudhe Kanitkar Associates is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Dixit Sneh Sankul Phase 11G+530 Apr 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Apr 202431 Aug 2024The Project building is 90%-92% complete as on 17/04/2024. Construction work is smoothly going on and building is expected to be fully complete within a month or so. The main rea

Location, Land & Connectivity

Located at Nene Ghat, Nene Ghat Road, Pune City, Pune, 411030. Per the filed land record, the plot is bounded to the north by Garden, to the south by Lane, to the east by CTS No 112 and to the west by CTS No 116. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park9 km
Baner–Balewadi belt9 km
Pune Int'l Airport (Lohegaon)10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sadashiv Peth

Gangadhar Apartments
possession by Aug 2026 · Kelkar Housing LLP
Krishna Kamal
possession by Sep 2026 · Vakratund Reality
Rukmini Niwas
possession by Sep 2026 · R. B. Chaphalkar Homes Pvt. Ltd.
SAI - Lalitha
possession by Dec 2026 · Sairam Developers
9 Sadashiv C Building
possession by Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
Pinnacle 9 Sadashiv A - Building
possession by Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.

Major developers building in Sadashiv Peth

Other RERA-registered projects in Pune

Diya Samruddhi
possession by Dec 2027 · Osian Diya Realty LLP
DK Elegance
declared completion Dec 2023 · Atmaram Manohar Gore
DLC Kashi Nagri
possession by Jun 2028 · Aadhar Mangalam Buildcorp LLP
DLC Wondernest A Building
possession by Dec 2029 · Goodwill Infracon
DLC Wondernest B Building
possession by Jun 2028 · Goodwill Infracon
DNK Capital
declared completion Mar 2026 · D N K Corp

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026