Pune/Project record

MahaRERA · the public record

Dnyandeep

Pune · M/s. Ira Spaces

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004712

Delivery and registration

When is the project declared for completion?

Dnyandeep is registered with MahaRERA as P52100004712 and the promoter has declared completion for 30 Oct 2022.

30 Oct 2022

declared completion

47months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004712
Registered on09 Aug 2017
Promoter-declared completion30 Oct 2022
Current statusCertificate Signed
Against todayabout 47 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dnyandeep record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Dnyandeep in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Dnyandeep1G+5-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Dnyandeep, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000009620231/10/2021Gaurav Ashok Shrowti and others vs M/S. Ira Spacesorder passed
CC00500000047150209/08/2024Ketaki R Kale vs Shekhar Pethepending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Sanction Plan Revised as per market conditions
30 Apr 202031 Oct 2021COVID SITUATION
31 Oct 202130 Oct 2022Covid 19

Location, Land & Connectivity

Located at Pune City, Pune, 411004. Per the filed land record, the plot is bounded to the north by Society Road, to the south by CTS 1441 and 1442, to the east by CTS 1439 part and to the west by CTS 1439 part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~80 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park80 km
Baner–Balewadi belt85 km
Pune Junction / city centre96 km
Pune Int'l Airport (Lohegaon)97 km
Kharadi / EON IT Park100 km
Magarpatta / Hadapsar IT101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Erandwane

Madhumati Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Serenity Springs
possession by Sep 2026 · Buttepatil Properties
State Bank OF India Employees Himgauri CO Operative Housing Society LTD
possession by Sep 2026 · Fortune Developers
Swojas Maitree
possession by Sep 2026 · Swojas Enterprises
THE Pleasant CO OP Housing Society LTD
possession by Sep 2026 · Shree Venkatesh Landmarks
Venkatesh Erandwane Central - Building-B1 - Phase 2
possession by Sep 2026 · Shree Venkatesh Buildcon PVT LTD

Major developers building in Erandwane

Other RERA-registered projects in Pune

Dnyandeep Dream
possession by Jun 2028 · Shambhuraj Developers
Dnyandeep Heights
possession by Dec 2028 · Mahalaxmi Venture
Dnyandeep Heritage
declared completion Dec 2024 · Mahalaxmi Associates
Dnyanesh
declared completion Mar 2025 · Nimit Group
Dnyanesh Residency
declared completion Dec 2020 · Siddhivinayak Associates
Dnyaneshwar
possession by Mar 2027 · Winstar Infra

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026