Dodke Prestige

Pune · Kaluram Eknath Dodke

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100047271

Delivery and registration

When is the project declared for completion?

Dodke Prestige is registered with MahaRERA as P52100047271 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100047271
Registered on17 Oct 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Dodke Prestige record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Kaluram Eknath Dodke is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Dodke Prestige in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Dodke Prestige1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Pune, Warje , Pune City, Pune, 411058. Per the filed land record, the plot is bounded to the north by Adj S No 137 P, to the south by 9 Meter Wide Road, to the east by Adj S No 137 P and to the west by Adj S No 137 P. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Warje

Libero
Not filing quarterly progress reports · possession by Dec 2026 · Satish Bora AND Associates
Ketan Heights Wing / Building No A
possession by Dec 2026 · Ketandevelopers
LE Phoenix
possession by Dec 2026 · Taksh Buildcon
Gulab Shilp
possession by Mar 2027 · Buttepatil Properties
Warje Business Bay
possession by Mar 2027 · Sanvi Developers
Cavansite Phase 2
possession by Jun 2027 · Arma Landmark LLP

Other RERA-registered projects in Pune

Dodke Shivratna
declared completion Dec 2020 · Dodke Associates
Dolphin Matrix
declared completion Jun 2026 · M/s. Mahalaxmi Promoters
Dolphin Palms Wing A AND B
possession by Dec 2029 · Dolphin Realty
Dolphin Palms Wings C, D AND E
possession by Mar 2027 · M/S Dolphin Realty
Dolphin Platina
declared completion Dec 2019 · Dolhin Home Developers
Dolphin Sereno
declared completion Jun 2026 · Dolphin Sereno LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.