MahaRERA Property Intelligence · Pune

DSK CHAITRABAN

P52100007124 · promoter Dskulkarniandcompany

Certificate SignedDue 30 Apr 2022

Delivery & Registration

MahaRERA registrationP52100007124
Registered on17 Aug 2017
Promoter-declared completion30 Apr 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dskulkarniandcompany is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
DSK Chaitraban-A1G+11-
DSK Chaitraban-Building B1G+11-

Complaints & Orders

10 complaints are on the MahaRERA record for this project, with orders passed in 10. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001117219/03/2018Vivek Ramesh Satpute vs M/s D.S.Kulkarni and Companyorder passed
CC00500000001105115/09/2018Mangesh Hajare vs Deepak Sakharam Kulkarniorder passed
CC00500000001123708/05/2018Cancellation of Flat in DSK Chaitraban Project vs DSK Developersorder passed
CC00500000001166002/07/2018PURUSHOTTAM PANDURANG BEDARE vs M/s DS Kulkarni & Companyorder passed
CC00500000001172514/07/2018mangesh suresh kate vs D S Kulkarni & Companyorder passed
CC00500000001195423/08/2018UJWALA YOGESH GOSAVI vs D.S. KULKARNI AND COMPANYorder passed
CC00500000002240302/01/2019Satish Vilas Pukale vs M/S D.S. Kulkarni and companyorder passed
CC00500000002266813/02/2019Mr. Satish Shriram Gogate & Mrs. Mrunal Satish Gogate vs M/s. D S Kulkarni & Associatesorder passed
CC00500000002266916/02/2019VILAS RAGHUNATH MADHEKAR/CHHAYA VILAS MADHEKAR vs D.S.KULKARNI & COMPANYorder passed
CC00500000010667021/02/2022SHEETAL JAYESH OSWAL vs D.S. KULKARNIorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
District And Session Court Pune322014Remand

Location, Land & Connectivity

Located at Pune City, Pune, 411042. Per the filed land record, the plot is bounded to the north by Gat No 531, to the south by Gat No 592 594 and 561, to the east by Gat No 550 and 561 and to the west by Gat No 481 and 530. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Baner–Balewadi belt10 km
Hinjewadi Rajiv Gandhi IT Park11 km
Pune Junction / city centre18 km
Magarpatta / Hadapsar IT23 km
Pune Int'l Airport (Lohegaon)24 km
Kharadi / EON IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dskulkarniandcompany is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Dskulkarniandcompany

Other RERA-registered projects in Ghorpade Peth

Sanghvi Premio
possession by Oct 2026 · Nitin Kantilal Sanghvi
Samaira Tower
possession by Nov 2026 · Prathamesh Constro Realty Llp
Shri Balaji Sudarshan
Deregistered by MahaRERA · possession by Dec 2026 · Shri Balaji Sudarshan
Radiance
Not filing quarterly progress reports · possession by Dec 2026 · Mohammed Sabir Husain Shaikh
Shree Swami Krupa Sadan
possession by Dec 2026 · A S Associates
Siddhi Plaza
possession by Dec 2026 · Shree Developers

Major developers building in Ghorpade Peth

Other RERA-registered projects in Pune

DSK Gold Leaf
declared completion Oct 2020 · D S Kulkarni Developers Limited
DSK Mayurban
declared completion Oct 2020 · D S Kulkarni Developers Limited
DSK Nabhangan
declared completion Apr 2022 · Dskulkarniandcompany
DSK Nandanvan
declared completion Oct 2020 · D S Kulkarni Developers Limited
DSK Pushpaban
declared completion Apr 2022 · Dskulkarni AND Associates
Dugad Heights
declared completion Dec 2025 · Dugad Reality

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026