MahaRERA Property Intelligence · Pune

ELEGANCE

P52100012555 · promoter Ulhas Dnyaneswar Konde

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP52100012555
Registered on04 Sep 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
ELEGENCE- A WING1G+14-
ELEGANCE -B WING1G+14-
ELEGANCE -C WING1G+17-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000011696018/04/2022Amarjit Ramchandra Deshmukh vs Yogayog Konde Deshmukh Devlopers Through Ulhas Dnyaneshwar Kondeorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202315 Aug 2019Due to market recession no flat has been sold. Which is affecting work .
30 Jun 202330 Jun 2023DUE TO COVID LOCKDOWN SITE WAS SHUT DOWN, AFTER UNLOCK WE STARTED THE WORK BUT OUR PROJECT MANANGEMENT CONSULTANT WAS DIED DUE TO COVID AS WELL AS ONE OF OUR CONTRACTOR DIED DUE TO

Location, Land & Connectivity

Located at Haveli, Pune, 412205. Per the filed land record, the plot is bounded to the north by 91 MTR, to the south by 67 MTR, to the east by 60 MTR NH4 WIDE ROAD and to the west by 57 MTR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT22 km
Pune Junction / city centre22 km
Kharadi / EON IT Park26 km
Baner–Balewadi belt26 km
Pune Int'l Airport (Lohegaon)29 km
Hinjewadi Rajiv Gandhi IT Park31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kapurhol

Royal Purandar
possession by Dec 2026 · Carcanet Infra Projects Private Limited
Shree Venkatesh SAI Residency
Not filing quarterly progress reports · possession by Mar 2027 · Shree Venkatesh SAI Associates
Balaji Dham Phase-1
possession by Mar 2027 · Garva Land Deal Private Limited
Industree
possession by Feb 2028 · Dhankawade Square Realtors LLP
Navkar Pleasure
possession by Dec 2028 · Parag Properties
Pooja Heavan Park
possession by Dec 2028 · Pooja Developers

Other RERA-registered projects in Pune

Elegance Park
declared completion Mar 2024 · M/S Ramoli Srushti Developers
Elegance Residency
declared completion Jul 2018 · Avirat Bhondve Ventures
Elegance Vega
possession by Dec 2026 · Elegance Landmarks
Elegant-9
declared completion Dec 2024 · Pradeep Kashinath Bhingare
Elegant Aariv
declared completion Jun 2025 · Elegant Builtcon
Elegant Residency Phase II
declared completion Sep 2024 · Arihant Vastushilp Propcon Private Limit

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026