Plotted Development Intelligence · Pune

ELITE II

P52100005920 · promoter Landmark Development Corporation

Certificate SignedDue 30 Dec 2026

Delivery & Registration

MahaRERA registrationP52100005920
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 412202. Per the filed land record, the plot is bounded to the north by GAONTHAN ROAD, to the south by 840 - 839, to the east by 840 and to the west by 840 . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park26 km
Magarpatta / Hadapsar IT26 km
Pune Int'l Airport (Lohegaon)30 km
Pune Junction / city centre32 km
Baner–Balewadi belt43 km
Hinjewadi Rajiv Gandhi IT Park48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Uruli Kanchan

Siddhi Sankul
possession by Sep 2026 · Jitendra Constructions AOP
Srinivas Empire
Not filing quarterly progress reports · possession by Mar 2027 · Srinivas And Associates
Sahyadri
possession by Aug 2027 · Sahyadri Builders And Developers
Needam - Block A - Wing B
possession by Dec 2027 · Raut Patil Constructions
Green Fantasy Phase-I
possession by Dec 2027 · Shree Mangalmurti Associates Phase-I
Rudra Samruddhi
possession by Dec 2027 · Shivrudra Constructions

Other RERA-registered projects in Pune

Elite Platinum
possession by Dec 2027 · Ganesh Dashrath Dale
Elite Regency
declared completion Jun 2026 · Kavya Buildcon
Elite Space
declared completion Dec 2021 · Spacemekk Developers
Elite Sparsh
possession by Dec 2028 · V P Realty Sparsh
Elite Square
declared completion Dec 2024 · Sunil Pandharinath Patil
Elite THE ARC
possession by Dec 2031 · 18 Elite Investments

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026