30 Sep 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100025351

Delivery and registration

When is the project declared for completion?

ELLORA SHOPEE is registered with MahaRERA as P52100025351 and the promoter has declared completion for 30 Sep 2026.

30 Sep 2026

declared completion

0months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100025351
Registered on30 Apr 2020
Promoter-declared completion30 Sep 2026
Current statusCertificate Signed
Against today0 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ELLORA SHOPEE record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Ellora Realities is the promoter of record on 134 projects registered with MahaRERA, 22 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

134projects

registered with MahaRERA

22flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ELLORA SHOPEE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A WING1G+431 Dec 2025
B WING1G+431 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PUNE, Sector -1 Peth, Haveli, Pune, 411026. Per the filed land record, the plot is bounded to the north by 24 Mtr Wide Road, to the south by S D C No 4 and Part of S D C No -5, to the east by S D C No - 3 and to the west by S D C No -1. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhosari

Atlantis
possession by Dec 2027 · Atharva Buildwell
Vision Ekaan
possession by Dec 2027 · Vision Creative Spaces
Santiago Skyworld
possession by Jun 2028 · Santiago Realtech
TEN BKC
possession by Dec 2029 · Mahalaxmi Land Developers
Shrikisan Enclave
declared completion Jul 2026 · M/s. Tirupathi Properties Through Prop M
Mahadeo Dreams
declared completion May 2026 · Shree Ganesh Associates

Other RERA-registered projects in Pune

Ellwood Homes
declared completion Dec 2023 · Shreeji Group
Elysia
declared completion Dec 2025 · Triaa Eliseo Housing LLP
Elysia Towers
declared completion Jun 2025 · Bhakti Builders
Elysium
declared completion Jun 2024 · Anand Yashwant Buchade
Emerald Bay Building 11
possession by Dec 2026 · Pune Projects LLP
Emerald Bay Building 12
possession by Dec 2029 · Pune Projects LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026