GOLDEN EAST

WANAWADI · VENKATESH VILAS AOP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018329

Delivery and registration

When is the project declared for completion?

GOLDEN EAST is registered with MahaRERA as P52100018329 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018329
Registered on23 Oct 2018
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOLDEN EAST record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Venkatesh Vilas Aop is the promoter of record on 161 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

161projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOLDEN EAST in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
GOLDEN EAST1G+1231 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r
31 Dec 202431 Dec 2028We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues

Location, Land & Connectivity

Located at WANAWADI, WANAWADI, Pune City, Pune, 411040. Per the filed land record, the plot is bounded to the north by 12 MTR ROAD AND SHIVARKAR HOSPITAL, to the south by PANAD ROAD AND APANG KALYANKARI SANSTHA, to the east by VILASRAO DESHMUKH KRIDA PRABHUDHANI and to the west by 30 FT ROAD AND SURVEY NO 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Pune Junction / city centre4 km
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park7 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt14 km
Hinjewadi Rajiv Gandhi IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wanawadi

Gold Crest
possession by Dec 2026 · Golden Magnum
Mainland Eternia
possession by Dec 2026 · Mainland Spaces LLP
Revanta
possession by Dec 2026 · Surana Landmarks LLP
The Deva Residences
possession by Dec 2026 · Suresh Devendra Kothari HUF
Ram Residency
possession by Jan 2027 · Opulent Builders
Ishanand
possession by Jun 2027 · Makawana Bros & CO

Other RERA-registered projects in Pune

Golden Empire
declared completion Jun 2019 · S K Developers
Golden Heights
declared completion May 2026 · Vastupurna Homes
Golden Highstreets
possession by Jul 2028 · Smart Sheds LLP
Golden Lake
possession by Dec 2027 · Narsinh Associates
Golden Lake Apartments
declared completion Feb 2021 · Arruj Promoters AND Developers
Golden Leaf
declared completion Apr 2024 · Golden Erectors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026