MahaRERA Property Intelligence · Pune

GULMOHAR RESIDENCY A WING

P52100022807 · AMBEGAON Bk. · promoter Deepak Ranchandra Dedge

Certificate SignedDue 12 Aug 2023

Delivery & Registration

MahaRERA registrationP52100022807
Registered on30 Oct 2019
Promoter-declared completion12 Aug 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
GULMOHAR RESIDENCY A WING1G+512 Aug 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at AMBEGAON Bk., AMBEGAN Bk., Pune City, Pune, 411046. Per the filed land record, the plot is bounded to the north by SNO 31, to the south by ROAD, to the east by ROAD and to the west by S NO 30. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Katraj

Aishwarya Heights
possession by Jul 2026 · Shree Sadguru Construction
Basil Chandrakant
possession by Jul 2026 · Shree Sadguru Developers
Vastushree Phase-1
possession by Aug 2026 · Vastu Construction
Capella
possession by Aug 2026 · D K Realties
Divya Elite
possession by Aug 2026 · RRS Infracon LLP
Yogamrut
Not filing quarterly progress reports · possession by Aug 2026 · Jay Ganesh Buildcon

Major developers building in Katraj

Other RERA-registered projects in Pune

Gulmohar Skypark
possession by Jun 2027 · LEO Construction
Gulmohar Society
possession by Dec 2027 · Nitin Sitaram Kulkarni
Gulmohar Square
declared completion Jun 2024 · Rajkumar Chamanlal Behr
Gulmohar Villas - A
declared completion Dec 2024 · Natraj Shamrao Satav
Gulmohar Villas - C
declared completion Dec 2024 · Nalini Chowdary Gogineni
Gulmohar Villas - D
declared completion Dec 2024 · Natraj Shamrao Satav

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026