Pune/Project record

MahaRERA · the public record

HILLCREST A AND B BUILDING

PIMPLE SAUDAGAR · P K GROUP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 18 September 2026
30 Nov 2027declared completionMahaRERA registration · read 12 Jul 2026
136registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100045782

Delivery and registration

When is the project declared for completion?

HILLCREST A AND B BUILDING is registered with MahaRERA as P52100045782 and the promoter has declared completion for 30 Nov 2027.

30 Nov 2027

declared completion

14months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100045782
Registered on09 Jun 2022
Promoter-declared completion30 Nov 2027
Current statusCertificate Signed
Against today14 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HILLCREST A AND B BUILDING record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Construction

How much construction cost has been reported?

In HILLCREST A AND B BUILDING, ₹78.45 Cr of a declared ₹78.54 Cr estimated project cost is reported as incurred, about 99.9%, as at the last certified filing with MahaRERA.

99.9%

₹78.45 Cr

of ₹78.54 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In HILLCREST A AND B BUILDING, 134 of 134 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

134 of 134 homes

₹202.50 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹197.73 Cr (about 98%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 134 registered agreements, the effective carpet rate is ₹13,870/sqft, with eight in ten falling between ₹10,823 and ₹15,541 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 2 not for sale.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 134 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in HILLCREST A AND B BUILDING is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 134 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 134 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 136 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A BUILDING1G+21102-
B BUILDING1G+2134-

Unit mix on the filing: 136 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PIMPLE SAUDAGAR, PIMPLE SAUDAGAR, Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by LAND OF CHANDRAKANT KATE, to the south by SURVEY NO 136 5, to the east by 18 mtrs WIDE ROAD and to the west by LAND OF VASANT KATE. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

P K Group is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by P K Group

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Hillcrest C Building
possession by Nov 2028 · P K Group
Hillcrest Manor
possession by Sep 2029 · NG Rathi Associates
Hillcrest Residency
declared completion Mar 2025 · Jijau Developers
Hills And Lakes
declared completion Jun 2026 · Rajnir Associates
Hills View
declared completion Mar 2025 · Shashi Builders & Developers
Hillshore 1,2,3,4,5,6,7,8,9,10,11 LCL - 0012
declared completion Dec 2025 · Lavasa Corporation Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026