HILLVIEW

PRABHAT ROAD · VENKATESHWARA BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006712

Delivery and registration

When is the project declared for completion?

HILLVIEW is registered with MahaRERA as P52100006712 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006712
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HILLVIEW record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Venkateshwara Builders is the promoter of record on 37 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

37projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HILLVIEW in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
HILLVIEW1G+1131 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for HILLVIEW, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000010652825/01/2022Canara Bank Officers C.H.S. vs Venkateshwara Builders - Abhijit Jadhavorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Revision of plan.

Location, Land & Connectivity

Located at PRABHAT ROAD, LANE NO 15, Pune City, Pune, 411004. Per the filed land record, the plot is bounded to the north by CTS 73 A, to the south by PLOT NO 108, to the east by CANAL ROAD and to the west by 9 M WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Venkateshwara Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Erandwane

Madhumati Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Serenity Springs
possession by Sep 2026 · Buttepatil Properties
State Bank OF India Employees Himgauri CO Operative Housing Society LTD
possession by Sep 2026 · Fortune Developers
Swojas Maitree
possession by Sep 2026 · Swojas Enterprises
THE Pleasant CO OP Housing Society LTD
possession by Sep 2026 · Shree Venkatesh Landmarks
Venkatesh Erandwane Central - Building-B1 - Phase 2
possession by Sep 2026 · Shree Venkatesh Buildcon PVT LTD

Major developers building in Erandwane

Other RERA-registered projects in Pune

Hillview Residency Building D
possession by Jun 2027 · Kumar Beharay Properties LLP
Hillview Residency Building E
possession by Jun 2027 · Kumar Beharay Properties LLP
Hillview Residency Building H
possession by Dec 2026 · Kumar Beharay Properties LLP
Hillview Residency Building I
possession by Dec 2026 · Kumar Beharay Properties LLP
Hillview Residency Phase I
declared completion May 2019 · Kumar Beharay Properties LLP
Himalaya Belmonte
possession by Dec 2026 · Vandan Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.