Pune/Project record

MahaRERA · the public record

ICON COMMERCIALJ4PART

Pune · AURIGAA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100001417

Delivery and registration

When is the project declared for completion?

ICON COMMERCIALJ4PART is registered with MahaRERA as P52100001417 and the promoter has declared completion for 31 Jan 2021.

31 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100001417
Registered on28 Jul 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ICON COMMERCIALJ4PART record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aurigaa Realtors is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ICON COMMERCIALJ4PART in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
ICONCOMMERCIALJ4PART1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by 45 MTR DP ROAD, to the south by BRT PARKING, to the east by 143 PART AND 144 PART and to the west by 143 PART AND 144 PART . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt4 km
Hinjewadi Rajiv Gandhi IT Park7 km
Pune Junction / city centre10 km
Pune Int'l Airport (Lohegaon)13 km
Kharadi / EON IT Park15 km
Magarpatta / Hadapsar IT16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aurigaa Realtors is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aurigaa Realtors

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Icon Estella
declared completion Dec 2023 · Icon Reality
Icon ORO
possession by Mar 2028 · Icon Ventures
Icon Residency
declared completion Jun 2025 · Icon Builders
Icon Tower
possession by Mar 2027 · Ayodhya Associates
Ideal Avenue
possession by Sep 2026 · Ideal Builders
Idyllic Coconut County
declared completion Dec 2025 · Idyllic Estates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026